iEvery work centre in both factories — Parramatta (fans, duct shop) and Carrington (Harveys Newcastle). Load is the shop hours still to do against each centre's weekly capacity; the queue is what's at that centre now. Click a job to move it on.
Late or at risk4
WO-26111 Series 1000 DWDI 1000 aerofoil — Mackay Dragline ServicesTest run · 10 h still to do · due 5 Oct (passed)
FanFBAWO-26114 Mill Exhaust 630 paddle wheel — Goodman Fielder — Erskine ParkReady to dispatch · 0 h still to do · due 5 Oct (passed)
FanFBAFAB-2618 Toilet exhaust risers — HAC-J2631Released · 40 h still to do · due 9 Oct
Duct shopHACHNF-2621 Level 3 lab supply ductwork — HN-J0412Folding & forming · 44 h still to do · due 9 Oct
Carrington fabHN Carrington — Harveys Newcastle (2,150 m² workshop)hours booked vs weekly capacity
| Work centre | Capacity /wk | This week | Next week | w/c 19 Oct | 26 Oct onward | At this centre now |
|---|---|---|---|---|---|---|
| CNC plasma (25 mm) Newcastle shop | 38 h | 0 h · 0% | 5 h · 14% | 21 h · 56% | 44 h · 115% | |
| Press brake, guillotine & punch Newcastle shop | 76 h | 15 h · 20% | 28 h · 37% | 55 h · 73% | 88 h · 115% | |
| Fabrication & welding Dale Woolaston + 4 | 190 h | 35 h · 18% | 172 h · 90% | 101 h · 53% | 161 h · 85% |