iEvery work centre in both factories — Parramatta (fans, duct shop) and Carrington (Harveys Newcastle). Load is the shop hours still to do against each centre's weekly capacity; the queue is what's at that centre now. Click a job to move it on.
Late or at risk4
WO-26111 Series 1000 DWDI 1000 aerofoil — Mackay Dragline ServicesTest run · 10 h still to do · due 5 Oct (passed)
FanFBAWO-26114 Mill Exhaust 630 paddle wheel — Goodman Fielder — Erskine ParkReady to dispatch · 0 h still to do · due 5 Oct (passed)
FanFBAFAB-2618 Toilet exhaust risers — HAC-J2631Released · 40 h still to do · due 9 Oct
Duct shopHACHNF-2621 Level 3 lab supply ductwork — HN-J0412Folding & forming · 44 h still to do · due 9 Oct
Carrington fabHN Parramatta — Fan & Blower factory and sheetmetal shophours booked vs weekly capacity
| Work centre | Capacity /wk | This week | Next week | w/c 19 Oct | 26 Oct onward | At this centre now |
|---|---|---|---|---|---|---|
| CNC plasma Steve Kowalski | 76 h | 6 h · 8% | 23 h · 30% | 15 h · 19% | 32 h · 42% | |
| Fabrication & welding Raj Patel + 3 | 152 h | 26 h · 17% | 117 h · 77% | 83 h · 54% | 82 h · 54% | +1 more |
| Duct line & folding Sheetmetal shop | 114 h | 24 h · 21% | 140 h · 123% | 47 h · 41% | 29 h · 25% | +2 more |
| Impeller balancing Mick Henderson | 38 h | 0 h · 0% | 16 h · 41% | 13 h · 35% | 15 h · 40% | |
| Fan assembly Ben Nguyen + 1 | 76 h | 0 h · 0% | 68 h · 89% | 33 h · 44% | 38 h · 50% | |
| Fan test bay Mick Henderson | 38 h | 15 h · 39% | 27 h · 71% | 13 h · 35% | 15 h · 40% |