Demo 06 Oct 2026
iEvery work centre in both factories — Parramatta (fans, duct shop) and Carrington (Harveys Newcastle). Load is the shop hours still to do against each centre's weekly capacity; the queue is what's at that centre now. Click a job to move it on.
Parramatta — Fan & Blower factory and sheetmetal shophours booked vs weekly capacity
Work centreCapacity /wkThis weekNext weekw/c 19 Oct26 Oct onwardAt this centre now
CNC plasma
Steve Kowalski
76 h
6 h · 8%
23 h · 30%
15 h · 19%
32 h · 42%
FAB-2611 Plantroom ductwork modifications · 6 h · due 12 OctWO-26104 AHU Fans 710 aerofoil · 5 h · due 19 OctWO-26103 Turbovane Radial Tip 1120 radial tip · 10 h · due 26 Oct
Fabrication & welding
Raj Patel + 3
152 h
26 h · 17%
117 h · 77%
83 h · 54%
82 h · 54%
FAB-2605 Fume exhaust ductwork (SS) · 12 h · due 6 OctWO-26106 Mill Exhaust 800 paddle wheel · 14 h · due 16 OctFAB-2615 Make-up air duct · 11 h · due 16 OctWO-26119 Series 1000 SWSI 630 aerofoil — KEF-FC1 Kitchen exhaust fan · 9 h · due 19 Oct +1 more
Duct line & folding
Sheetmetal shop
114 h
24 h · 21%
140 h · 123%
47 h · 41%
29 h · 25%
FAB-2607 Kitchen exhaust duct (fire-rated) · 8 h · due 12 OctFAB-2608 Food court exhaust risers · 6 h · due 12 OctFAB-2610 Carpark supply & exhaust ducts · 17 h · due 12 OctFAB-2617 AHU-C2 discharge plenum · 20 h · due 16 Oct +2 more
Impeller balancing
Mick Henderson
38 h
0 h · 0%
16 h · 41%
13 h · 35%
15 h · 40%
WO-26107 Series 101 Pressure Blower 820 radial tip · 3 h · due 12 OctWO-26108 Series 1000 SWSI 630 aerofoil · 9 h · due 15 Oct
Fan assembly
Ben Nguyen + 1
76 h
0 h · 0%
68 h · 89%
33 h · 44%
38 h · 50%
WO-26109 Turbovane Radial Tip 1250 radial tip · 19 h · due 12 OctWO-26125 Plug Fans 630 aerofoil — HAE-01 Hot aisle exhaust fan · 4 h · due 12 OctWO-26110 Plug Fans 560 aerofoil · 6 h · due 14 Oct
Fan test bay
Mick Henderson
38 h
15 h · 39%
27 h · 71%
13 h · 35%
15 h · 40%
WO-26111 Series 1000 DWDI 1000 aerofoil · 10 h · due 5 OctWO-26112 Series 1000 SWSI 1250 aerofoil · 5 h · due 9 Oct