Harvey

HAC-J2611

Parramatta Square 6 — Levels 14–16 fitout · Built Pty Ltd
Demo 06 Oct 2026
← Contracts
1
Enquiry
direct order
✓
Quote
3
Jobin progress
5
Look after it
not yet
Next step
Raise this month's progress claim — $45,555 to claim
Work done to date 62% ($759,252); claimed so far $713,697. Retention 5% is held automatically.
ContractInstallationOn track
Client
Built Pty Ltd · Sam Whitlock
Site
6 Parramatta Sq, Parramatta
Project manager
Greg Pollard
Program
02 Jul 2026 → PC 13 Nov 2026
Scope
Chilled beam fitout to three floors, FCUs to meeting rooms, OA & general exhaust, BMCS integration.
From quote
HAC-Q2641
62% complete
MoneyForecast margin 19.7%
Contract value$1,186,000.00 Approved variations$38,600.00 Revised contract$1,224,600.00 Cost budget (from estimate)$1,000,700.00 Cost to date$602,858.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$983,124.00 Earned (62%)$759,252.00 Claimed to date$713,696.88 Retention held by client$35,684.84
Equipment $209,562 FBA fans (inter-company) $3,964 Ductwork (Parramatta shop) $101,188 Site labour $145,079 Controls subcontract $51,644 Electrical subcontract $37,431 Cranage & rigging $21,258 Pipework & materials $32,732
Equipment schedule1 FBA fan line(s) · 0 not yet ordered
TagTypeMake / modelLocationkWSupplyFBA works orderSerial
FCU-14-01..12 (×12) Fan coil unit OPA 450 FCU Levels 14–16 0.4 Supplier — —
EF-14-01 Toilet exhaust fan In-line Centrifugal 450 backward inclined Level 16 plant 1.1 FBA WO-26115 · Dispatched FBA-26-0407
Costs to date$602,858
DateCategoryDescriptionAmount
16 Sep 2026 FBA fans (inter-company) WO-26115 In-line Centrifugal 450 backward inclined — EF-14-01 Toilet exhaust fan $3,964
17 Aug 2026 Site labour Site labour — weeks 7–9 $49,772
17 Aug 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 3 $35,983
11 Aug 2026 Pipework & materials Pipework & materials — claim 2 $16,351
11 Aug 2026 Cranage & rigging Cranage & rigging — claim 2 $11,059
11 Aug 2026 Electrical subcontract Electrical subcontract — claim 2 $18,076
11 Aug 2026 Controls subcontract Controls subcontract — claim 2 $24,171
11 Aug 2026 Equipment Progress claim — FCUs $101,060
03 Aug 2026 Site labour Site labour — weeks 4–6 $46,822
03 Aug 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 2 $29,962
22 Jul 2026 Pipework & materials Pipework & materials — claim 1 $16,381
22 Jul 2026 Cranage & rigging Cranage & rigging — claim 1 $10,199
22 Jul 2026 Electrical subcontract Electrical subcontract — claim 1 $19,355
22 Jul 2026 Controls subcontract Controls subcontract — claim 1 $27,473
22 Jul 2026 Equipment Supply — FCUs $108,502
17 Jul 2026 Site labour Site labour — weeks 1–3 $48,485
17 Jul 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 1 $35,243
Emails & activity · 9
↗ RFI 017 — HAC-J2611 — Variation: additional FCU to comms room per tenant request Greg Pollard → Sam Whitlock HAC synced 08 Aug 2026 · 12:32
From Greg Pollard <gpollard@harveyind.com.au> · To Sam Whitlock <sam@built.com.au>
Hi Sam, Variation: additional FCU to comms room per tenant request Marked-up drawing attached. Greg Pollard
◷ Site coordination meeting — Parramatta Square 6 Meeting · Sam Whitlock · Greg Pollard HAC 06 Aug 2026 · 07:30
Attendees: Sam Whitlock, Greg Pollard, Luke Brennan. Commissioning dates agreed with BMS subcontractor.
↙ RFI 014 — HAC-J2611 — Access to plantroom for crane lift Sam Whitlock → Greg Pollard HAC synced 25 Jul 2026 · 13:29
From Sam Whitlock <sam@built.com.au> · To Greg Pollard <gpollard@harveyind.com.au>
Hi Greg, Access to plantroom for crane lift — Saturday OK? Please advise by end of week. Sam Whitlock
◷ Site coordination meeting — Parramatta Square 6 Meeting · Sam Whitlock · Greg Pollard HAC 23 Jul 2026 · 07:30
Attendees: Sam Whitlock, Greg Pollard, Luke Brennan. Commissioning dates agreed with BMS subcontractor.
↗ RFI 011 — HAC-J2611 — Ceiling void clash with sprinkler main on grid C Greg Pollard → Sam Whitlock HAC synced 11 Jul 2026 · 10:10
From Greg Pollard <gpollard@harveyind.com.au> · To Sam Whitlock <sam@built.com.au>
Hi Sam, Ceiling void clash with sprinkler main on grid C — can ductwork drop 150mm? Marked-up drawing attached. Greg Pollard
◷ Site coordination meeting — Parramatta Square 6 Meeting · Sam Whitlock · Greg Pollard HAC 09 Jul 2026 · 07:30
Attendees: Sam Whitlock, Greg Pollard, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↗ Re: Quotation HAC-Q2641 — Parramatta Square 6 — Levels 14–16 fitout Rowan Kennedy → Sam Whitlock HAC synced 10 Jun 2026 · 16:10
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Sam Whitlock <sam@built.com.au>
Thanks Sam — appreciated. Greg Pollard will be your project manager and will be in touch this week. Rowan Kennedy
↙ Re: Quotation HAC-Q2641 — Parramatta Square 6 — Levels 14–16 fitout Sam Whitlock → Rowan Kennedy HAC synced 10 Jun 2026 · 10:00
From Sam Whitlock <sam@built.com.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan, Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule. Sam Whitlock
↗ Quotation HAC-Q2641 — Parramatta Square 6 — Levels 14–16 fitout Rowan Kennedy → Sam Whitlock HAC sent 23 May 2026 · 14:34
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Sam Whitlock <sam@built.com.au>
Hi Sam, Please find attached our quotation HAC-Q2641 for Parramatta Square 6 — Levels 14–16 fitout — $1,186,000 + GST, valid 30 days. Happy to walk through it. Regards, Rowan Kennedy