1
Enquiry
direct order
✓
Quote
5
Look after it
not yet
Status
Paid 05 Oct 2026
Harvey Air Conditioning Pty Ltd · Harvey Air Conditioning
Cnr Macarthur & Fennell Sts, Parramatta NSW 2150 · (02) 9630 5100 · air@harveyind.com.au
ABN 42 000 473 334 · ARCtick AU10031
Tax invoice
HAC-58211
Date 25 Aug 2026
Due 15 Oct 2026
Your order HAC-J2611
Bill to
Built Pty Ltd
Attn: Sam Whitlock
sam@built.com.au
Sydney NSW
ABN 56 440 190 456
Re
Progress claim 2 — Parramatta Square 6 — Levels 14–16 fitoutHAC-J2611
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Progress claim 2: work completed to date 39% | 1 | $245,967.41 | $245,967.41 |
| Less retention 5% | 1 | −$12,298.37 | −$12,298.37 |
| Subtotal (ex GST) | $233,669.04 |
| GST 10% | $23,366.90 |
| Total (inc GST) | $257,035.94 |
Payment — EFT to Harvey Air Conditioning Pty Ltd, Westpac — Parramatta, BSB 032-078, Acct 41 6228. Please quote HAC-58211 as the reference.
PAID 05 Oct 2026 — thank you.
Emails & activity · 7
↗ Tax invoice HAC-58211 — Progress claim 2 — Parramatta Square 6 — Levels 14–16 fitout HAC sent 25 Aug 2026 · 16:48
From Karen Mills <kmills@harveyind.com.au> · To Sam Whitlock <sam@built.com.au>
Hi,
Please find attached tax invoice HAC-58211 for $257,035.94 inc GST, due 15/10/2026.
Karen Mills
Accounts — Harvey Industries↗ RFI 017 — HAC-J2611 — Variation: additional FCU to comms room per tenant request HAC synced 08 Aug 2026 · 12:32
From Greg Pollard <gpollard@harveyind.com.au> · To Sam Whitlock <sam@built.com.au>
Hi Sam,
Variation: additional FCU to comms room per tenant request
Marked-up drawing attached.
Greg Pollard◷ Site coordination meeting — Parramatta Square 6 HAC 06 Aug 2026 · 07:30
Attendees: Sam Whitlock, Greg Pollard, Luke Brennan. Commissioning dates agreed with BMS subcontractor.
↙ RFI 014 — HAC-J2611 — Access to plantroom for crane lift HAC synced 25 Jul 2026 · 13:29
From Sam Whitlock <sam@built.com.au> · To Greg Pollard <gpollard@harveyind.com.au>
Hi Greg,
Access to plantroom for crane lift — Saturday OK?
Please advise by end of week.
Sam Whitlock◷ Site coordination meeting — Parramatta Square 6 HAC 23 Jul 2026 · 07:30
Attendees: Sam Whitlock, Greg Pollard, Luke Brennan. Commissioning dates agreed with BMS subcontractor.
↗ RFI 011 — HAC-J2611 — Ceiling void clash with sprinkler main on grid C HAC synced 11 Jul 2026 · 10:10
From Greg Pollard <gpollard@harveyind.com.au> · To Sam Whitlock <sam@built.com.au>
Hi Sam,
Ceiling void clash with sprinkler main on grid C — can ductwork drop 150mm?
Marked-up drawing attached.
Greg Pollard◷ Site coordination meeting — Parramatta Square 6 HAC 09 Jul 2026 · 07:30
Attendees: Sam Whitlock, Greg Pollard, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.