1
Enquiry
—
2
Quotenext
not yet
3
Job
not yet
✓
Look after it
Status
PPM visit booked
It's on the Service board — the asset dates roll forward when the visit is completed.
AgreementHarvey AirCon ServiceActive
Site
20 Smith St Parramatta
20 Smith St, Parramatta NSW
Customer
CBRE · Marcus Webb
Term
15 Oct 2025 → 15 Oct 2026
Value
$52,400 a year · billed monthly
Scope
PPM per AIRAH DA19, monthly cooling tower inspection & water treatment log
Asset register — 9 assetsbarcode scanned at each service
BarcodeAssetMakeModelSerialLocationDA19 frequencyLast serviceNext due
HA-004290 AHU Air Change AHU 8417445 Roof #3 Quarterly 10 Jul 2026 09 Oct 2026 Scheduled
HA-004287 Cooling tower Aquacool — 5693795 Plantroom #2 Monthly 11 Sep 2026 11 Oct 2026 Scheduled
HA-004292 AHU Air Change AHU 1540731 Mezzanine #5 Quarterly 21 Jul 2026 20 Oct 2026 Scheduled
HA-004286 Cooling tower Aquacool — 5301831 Plantroom #1 Monthly 25 Sep 2026 25 Oct 2026 Scheduled
HA-004289 AHU Air Change AHU 3038575 Level 2 plant #2 Quarterly 29 Jul 2026 28 Oct 2026 Scheduled
HA-004285 Chiller (Powerpax) Powerpax centrifugal 1268939 Plantroom Monthly 01 Oct 2026 31 Oct 2026 Scheduled
HA-004288 AHU Air Change AHU 6964881 Mezzanine #1 Quarterly 25 Aug 2026 24 Nov 2026 Scheduled
HA-004291 AHU Air Change AHU 4702490 Mezzanine #4 Quarterly 27 Sep 2026 27 Dec 2026 Scheduled
HA-004293 AHU Air Change AHU 8889842 Level 2 plant #6 Quarterly 02 Oct 2026 01 Jan 2027 Scheduled