1
Enquiry
direct order
✓
Quote
✓
Job
5
Look after itnext
not yet
Next step
Waiting for payment — due 15 Nov 2026
Mark it paid when it shows in the bank.
Harvey Air Conditioning Pty Ltd · Harvey Air Conditioning
Cnr Macarthur & Fennell Sts, Parramatta NSW 2150 · (02) 9630 5100 · air@harveyind.com.au
ABN 42 000 473 334 · ARCtick AU10031
Tax invoice
HAC-58242
Date 25 Sep 2026
Due 15 Nov 2026
Your order HAC-J2634
Bill to
Shape Australia
Attn: Nicole Bryant
nicole@shape.com.au
North Sydney NSW
ABN 10 276 836 777
Re
Progress claim 7 — NBN Blacktown exchange — CRAC replacementHAC-J2634
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Progress claim 7: work completed to date 100% | 1 | $74,499.17 | $74,499.17 |
| Less retention 5% | 1 | −$3,724.96 | −$3,724.96 |
| Subtotal (ex GST) | $70,774.21 |
| GST 10% | $7,077.42 |
| Total (inc GST) | $77,851.63 |
Payment — EFT to Harvey Air Conditioning Pty Ltd, Westpac — Parramatta, BSB 032-078, Acct 41 6228. Please quote HAC-58242 as the reference.
Emails & activity · 7
↗ Tax invoice HAC-58242 — Progress claim 7 — NBN Blacktown exchange — CRAC replacement HAC sent 25 Sep 2026 · 15:54
From Karen Mills <kmills@harveyind.com.au> · To Nicole Bryant <nicole@shape.com.au>
Hi,
Please find attached tax invoice HAC-58242 for $77,851.63 inc GST, due 15/11/2026.
Karen Mills
Accounts — Harvey Industries↗ RFI 029 — HAC-J2634 — BMS points list HAC synced 16 Apr 2026 · 15:21
From Greg Pollard <gpollard@harveyind.com.au> · To Nicole Bryant <nicole@shape.com.au>
Hi Nicole,
BMS points list — confirm naming convention
Marked-up drawing attached.
Greg Pollard◷ Site coordination meeting — NBN Blacktown exchange HAC 14 Apr 2026 · 07:30
Attendees: Nicole Bryant, Greg Pollard, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↙ RFI 026 — HAC-J2634 — Fire mode testing date with certifier HAC synced 02 Apr 2026 · 14:06
From Nicole Bryant <nicole@shape.com.au> · To Greg Pollard <gpollard@harveyind.com.au>
Hi Greg,
Fire mode testing date with certifier
Please advise by end of week.
Nicole Bryant◷ Site coordination meeting — NBN Blacktown exchange HAC 31 Mar 2026 · 07:30
Attendees: Nicole Bryant, Greg Pollard, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↗ RFI 023 — HAC-J2634 — BMS points list HAC synced 19 Mar 2026 · 12:19
From Greg Pollard <gpollard@harveyind.com.au> · To Nicole Bryant <nicole@shape.com.au>
Hi Nicole,
BMS points list — confirm naming convention
Marked-up drawing attached.
Greg Pollard◷ Site coordination meeting — NBN Blacktown exchange HAC 17 Mar 2026 · 07:30
Attendees: Nicole Bryant, Greg Pollard, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.