Hand over to Harvey AirCon Service
Practical completion reached. 4 equipment line(s) become barcoded assets with a PPM schedule.
ContractPractical CompletionOn track
- Client
- Burwood RSL Club · Steve Antoniou
- Site
- 96 Shaftesbury Rd, Burwood
- Project manager
- Matt Corrigan
- Program
- 18 Jun 2026 → PC 30 Sep 2026
- Scope
- Replace AHU-1/2 incl. FBA DWDI supply fans, new chilled water coils, VSDs.
- From quote
- HAC-Q2648
100% complete
MoneyForecast margin 22.6%
Contract value$298,000.00 Approved variations$14,100.00 Revised contract$312,100.00 Cost budget (from estimate)$253,000.00 Cost to date$241,553.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$241,553.00 Earned (100%)$312,100.00 Claimed to date$312,100.00 Retention held by client$15,605.00
Equipment $76,961 FBA fans (inter-company) $25,560 Ductwork (Parramatta shop) $32,879 Site labour $51,742 Controls subcontract $17,452 Electrical subcontract $14,782 Cranage & rigging $8,805 Pipework & materials $13,372
Equipment schedule2 FBA fan line(s) · 0 not yet ordered
| Tag | Type | Make / model | Location | kW | Supply | FBA works order | Serial | |
|---|---|---|---|---|---|---|---|---|
| AHU-1 | Air handling unit | Custom 9.5 kL/s | Auditorium plant | 11 | Supplier | — | — | |
| AHU-2 | Air handling unit | Custom 9.5 kL/s | Auditorium plant | 11 | Supplier | — | — | |
| SF-1 | AHU supply fan | Series 1000 DWDI 710 aerofoil | AHU-1 | 11 | FBA | WO-26123 · Dispatched | FBA-26-0413 | |
| SF-2 | AHU supply fan | Series 1000 DWDI 710 aerofoil | AHU-2 | 11 | FBA | WO-26124 · Dispatched | FBA-26-0414 | |
Costs to date$241,553
| Date | Category | Description | Amount | |
|---|---|---|---|---|
| 07 Aug 2026 | FBA fans (inter-company) | WO-26124 Series 1000 DWDI 710 aerofoil — SF-2 AHU supply fan | $12,780 | |
| 07 Aug 2026 | FBA fans (inter-company) | WO-26123 Series 1000 DWDI 710 aerofoil — SF-1 AHU supply fan | $12,780 | |
| 03 Aug 2026 | Site labour | Site labour — weeks 7–9 | $15,067 | |
| 03 Aug 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 3 | $11,335 | |
| 28 Jul 2026 | Pipework & materials | Pipework & materials — claim 2 | $6,835 | |
| 28 Jul 2026 | Cranage & rigging | Cranage & rigging — claim 2 | $4,038 | |
| 28 Jul 2026 | Electrical subcontract | Electrical subcontract — claim 2 | $7,558 | |
| 28 Jul 2026 | Controls subcontract | Controls subcontract — claim 2 | $9,007 | |
| 28 Jul 2026 | Equipment | Progress claim — FCUs | $38,702 | |
| 20 Jul 2026 | Site labour | Site labour — weeks 4–6 | $18,078 | |
| 20 Jul 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 2 | $10,417 | |
| 08 Jul 2026 | Pipework & materials | Pipework & materials — claim 1 | $6,537 | |
| 08 Jul 2026 | Cranage & rigging | Cranage & rigging — claim 1 | $4,767 | |
| 08 Jul 2026 | Electrical subcontract | Electrical subcontract — claim 1 | $7,224 | |
| 08 Jul 2026 | Controls subcontract | Controls subcontract — claim 1 | $8,445 | |
| 08 Jul 2026 | Equipment | Delivery — CRAC units | $38,259 | |
| 03 Jul 2026 | Site labour | Site labour — weeks 1–3 | $18,597 | |
| 03 Jul 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 1 | $11,127 | |
Emails & activity · 9
↗ RFI 024 — HAC-J2627 — Variation: additional FCU to comms room per tenant request HAC synced 25 Jul 2026 · 15:57
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Steve Antoniou <steve@burwoodrsl.com.au>
Hi Steve,
Variation: additional FCU to comms room per tenant request
Marked-up drawing attached.
Matt Corrigan◷ Site coordination meeting — Burwood RSL HAC 23 Jul 2026 · 07:30
Attendees: Steve Antoniou, Matt Corrigan, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↙ RFI 021 — HAC-J2627 — Fire mode testing date with certifier HAC synced 11 Jul 2026 · 09:21
From Steve Antoniou <steve@burwoodrsl.com.au> · To Matt Corrigan <mcorrigan@harveyind.com.au>
Hi Matt,
Fire mode testing date with certifier
Please advise by end of week.
Steve Antoniou◷ Site coordination meeting — Burwood RSL HAC 09 Jul 2026 · 07:30
Attendees: Steve Antoniou, Matt Corrigan, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↗ RFI 018 — HAC-J2627 — Variation: additional FCU to comms room per tenant request HAC synced 27 Jun 2026 · 13:11
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Steve Antoniou <steve@burwoodrsl.com.au>
Hi Steve,
Variation: additional FCU to comms room per tenant request
Marked-up drawing attached.
Matt Corrigan◷ Site coordination meeting — Burwood RSL HAC 25 Jun 2026 · 07:30
Attendees: Steve Antoniou, Matt Corrigan, Luke Brennan. Plant delivery confirmed for crane lift; road closure permit lodged.
↗ Re: Quotation HAC-Q2648 — Burwood RSL — auditorium AHU replacement HAC synced 26 May 2026 · 16:38
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Steve Antoniou <steve@burwoodrsl.com.au>
Thanks Steve — appreciated. Greg Pollard will be your project manager and will be in touch this week.
Rowan Kennedy↙ Re: Quotation HAC-Q2648 — Burwood RSL — auditorium AHU replacement HAC synced 26 May 2026 · 10:00
From Steve Antoniou <steve@burwoodrsl.com.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan,
Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule.
Steve Antoniou↗ Quotation HAC-Q2648 — Burwood RSL — auditorium AHU replacement HAC sent 09 Apr 2026 · 14:31
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Steve Antoniou <steve@burwoodrsl.com.au>
Hi Steve,
Please find attached our quotation HAC-Q2648 for Burwood RSL — auditorium AHU replacement — $298,000 + GST, valid 30 days.
Happy to walk through it.
Regards,
Rowan Kennedy