Harvey

HAC-J2623

Lincoln Rise Stage 2 — 64 apartments · EDT Projects
Demo 06 Oct 2026
← Contracts
1
Enquiry
direct order
✓
Quote
3
Jobin progress
5
Look after it
not yet
Next step
Raise this month's progress claim — $33,616 to claim
Work done to date 66% ($560,274); claimed so far $526,658. Retention 5% is held automatically.
ContractInstallationAt risk
Client
EDT Projects · Elias Daher
Site
16–20 Withers Rd, Kellyville
Project manager
Greg Pollard
Program
08 Jun 2026 → PC 30 Oct 2026
Scope
Multi-head split per apartment, carpark ventilation (FBA jet & supply fans).
From quote
HAC-Q2646
66% complete
MoneyForecast margin 13.8%
Contract value$812,000.00 Approved variations$36,900.00 Revised contract$848,900.00 Cost budget (from estimate)$695,700.00 Cost to date$494,926.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$731,464.00 Earned (66%)$560,274.00 Claimed to date$526,657.56 Retention held by client$26,332.88
Equipment $165,427 FBA fans (inter-company) $26,294 Ductwork (Parramatta shop) $77,089 Site labour $113,510 Controls subcontract $39,147 Electrical subcontract $26,342 Cranage & rigging $17,780 Pipework & materials $29,337
Equipment schedule2 FBA fan line(s) · 0 not yet ordered
TagTypeMake / modelLocationkWSupplyFBA works orderSerial
CPS-01 Carpark supply fan Series 1000 DWDI 800 aerofoil Basement 1 11 FBA WO-26121 · Dispatched FBA-26-0411
CPE-01 Carpark exhaust fan Series 1000 SWSI 800 aerofoil Basement 2 11 FBA WO-26122 · Dispatched FBA-26-0412
Costs to date$494,926
DateCategoryDescriptionAmount
17 Aug 2026 FBA fans (inter-company) WO-26122 Series 1000 SWSI 800 aerofoil — CPE-01 Carpark exhaust fan $11,376
17 Aug 2026 FBA fans (inter-company) WO-26121 Series 1000 DWDI 800 aerofoil — CPS-01 Carpark supply fan $14,918
23 Jul 2026 Site labour Site labour — weeks 7–9 $38,971
23 Jul 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 3 $28,719
20 Jul 2026 Pipework & materials Pipework & materials — claim 2 $14,861
20 Jul 2026 Cranage & rigging Cranage & rigging — claim 2 $8,514
20 Jul 2026 Electrical subcontract Electrical subcontract — claim 2 $13,654
20 Jul 2026 Controls subcontract Controls subcontract — claim 2 $17,474
20 Jul 2026 Equipment Delivery — packaged units $82,806
08 Jul 2026 Site labour Site labour — weeks 4–6 $40,475
08 Jul 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 2 $25,721
29 Jun 2026 Pipework & materials Pipework & materials — claim 1 $14,476
29 Jun 2026 Cranage & rigging Cranage & rigging — claim 1 $9,266
29 Jun 2026 Electrical subcontract Electrical subcontract — claim 1 $12,688
29 Jun 2026 Controls subcontract Controls subcontract — claim 1 $21,673
29 Jun 2026 Equipment Progress claim — packaged units $82,621
23 Jun 2026 Site labour Site labour — weeks 1–3 $34,064
23 Jun 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 1 $22,649
Emails & activity · 10
✎ Account note — cost overrun Note · Elias Daher · Peter Harvey HAC 04 Oct 2026 · 08:15
Splits install running over on labour (access delays from builder). Raise variation for standby time before next claim.
↗ RFI 022 — HAC-J2623 — Variation: additional FCU to comms room per tenant request Greg Pollard → Elias Daher HAC synced 15 Jul 2026 · 11:40
From Greg Pollard <gpollard@harveyind.com.au> · To Elias Daher <elias@edtprojects.com.au>
Hi Elias, Variation: additional FCU to comms room per tenant request Marked-up drawing attached. Greg Pollard
◷ Site coordination meeting — Lincoln Rise Stage 2 Meeting · Elias Daher · Greg Pollard HAC 13 Jul 2026 · 07:30
Attendees: Elias Daher, Greg Pollard, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↙ RFI 019 — HAC-J2623 — BMS points list Elias Daher → Greg Pollard HAC synced 01 Jul 2026 · 13:07
From Elias Daher <elias@edtprojects.com.au> · To Greg Pollard <gpollard@harveyind.com.au>
Hi Greg, BMS points list — confirm naming convention Please advise by end of week. Elias Daher
◷ Site coordination meeting — Lincoln Rise Stage 2 Meeting · Elias Daher · Greg Pollard HAC 29 Jun 2026 · 07:30
Attendees: Elias Daher, Greg Pollard, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↗ RFI 016 — HAC-J2623 — Confirm chilled beam supply temperature for L15 tenancy Greg Pollard → Elias Daher HAC synced 17 Jun 2026 · 15:25
From Greg Pollard <gpollard@harveyind.com.au> · To Elias Daher <elias@edtprojects.com.au>
Hi Elias, Confirm chilled beam supply temperature for L15 tenancy Marked-up drawing attached. Greg Pollard
◷ Site coordination meeting — Lincoln Rise Stage 2 Meeting · Elias Daher · Greg Pollard HAC 15 Jun 2026 · 07:30
Attendees: Elias Daher, Greg Pollard, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↗ Re: Quotation HAC-Q2646 — Lincoln Rise Stage 2 — 64 apartments Rowan Kennedy → Elias Daher HAC synced 15 May 2026 · 16:26
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Elias Daher <elias@edtprojects.com.au>
Thanks Elias — appreciated. Greg Pollard will be your project manager and will be in touch this week. Rowan Kennedy
↙ Re: Quotation HAC-Q2646 — Lincoln Rise Stage 2 — 64 apartments Elias Daher → Rowan Kennedy HAC synced 15 May 2026 · 10:00
From Elias Daher <elias@edtprojects.com.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan, Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule. Elias Daher
↗ Quotation HAC-Q2646 — Lincoln Rise Stage 2 — 64 apartments Rowan Kennedy → Elias Daher HAC sent 25 Apr 2026 · 17:31
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Elias Daher <elias@edtprojects.com.au>
Hi Elias, Please find attached our quotation HAC-Q2646 for Lincoln Rise Stage 2 — 64 apartments — $812,000 + GST, valid 30 days. Happy to walk through it. Regards, Rowan Kennedy