Quote accepted
HAC-Q2646
✓
Contract
Installation
✓
FBA fans
2/2 delivered
4
Practical completion
30 Oct 2026
5
Service handover
pending
ContractInstallationAt risk
- Client
- EDT Projects · Elias Daher
- Site
- 16–20 Withers Rd, Kellyville
- Project manager
- Greg Pollard
- Program
- 08 Jun 2026 → PC 30 Oct 2026
- Scope
- Multi-head split per apartment, carpark ventilation (FBA jet & supply fans).
- From quote
- HAC-Q2646
66% complete
MoneyForecast margin 13.8%
Contract value$812,000.00 Approved variations$36,900.00 Revised contract$848,900.00 Cost budget (from estimate)$695,700.00 Cost to date$494,926.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$731,464.00 Earned (66%)$560,274.00 Claimed to date$526,657.56 Retention held by client$26,332.88
Equipment $165,427 FBA fans (inter-company) $26,294 Ductwork (Parramatta shop) $77,089 Site labour $113,510 Controls subcontract $39,147 Electrical subcontract $26,342 Cranage & rigging $17,780 Pipework & materials $29,337
Equipment schedule2 FBA fan line(s) · 0 not yet ordered
| Tag | Type | Make / model | Location | kW | Supply | FBA works order | Serial | |
|---|---|---|---|---|---|---|---|---|
| CPS-01 | Carpark supply fan | Series 1000 DWDI 800 aerofoil | Basement 1 | 11 | FBA | WO-26121 · Dispatched | FBA-26-0411 | |
| CPE-01 | Carpark exhaust fan | Series 1000 SWSI 800 aerofoil | Basement 2 | 11 | FBA | WO-26122 · Dispatched | FBA-26-0412 | |
Costs to date$494,926
| Date | Category | Description | Amount | |
|---|---|---|---|---|
| 17 Aug 2026 | FBA fans (inter-company) | WO-26122 Series 1000 SWSI 800 aerofoil — CPE-01 Carpark exhaust fan | $11,376 | |
| 17 Aug 2026 | FBA fans (inter-company) | WO-26121 Series 1000 DWDI 800 aerofoil — CPS-01 Carpark supply fan | $14,918 | |
| 23 Jul 2026 | Site labour | Site labour — weeks 7–9 | $38,971 | |
| 23 Jul 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 3 | $28,719 | |
| 20 Jul 2026 | Pipework & materials | Pipework & materials — claim 2 | $14,861 | |
| 20 Jul 2026 | Cranage & rigging | Cranage & rigging — claim 2 | $8,514 | |
| 20 Jul 2026 | Electrical subcontract | Electrical subcontract — claim 2 | $13,654 | |
| 20 Jul 2026 | Controls subcontract | Controls subcontract — claim 2 | $17,474 | |
| 20 Jul 2026 | Equipment | Delivery — packaged units | $82,806 | |
| 08 Jul 2026 | Site labour | Site labour — weeks 4–6 | $40,475 | |
| 08 Jul 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 2 | $25,721 | |
| 29 Jun 2026 | Pipework & materials | Pipework & materials — claim 1 | $14,476 | |
| 29 Jun 2026 | Cranage & rigging | Cranage & rigging — claim 1 | $9,266 | |
| 29 Jun 2026 | Electrical subcontract | Electrical subcontract — claim 1 | $12,688 | |
| 29 Jun 2026 | Controls subcontract | Controls subcontract — claim 1 | $21,673 | |
| 29 Jun 2026 | Equipment | Progress claim — packaged units | $82,621 | |
| 23 Jun 2026 | Site labour | Site labour — weeks 1–3 | $34,064 | |
| 23 Jun 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 1 | $22,649 | |
Emails & activity · 10
✎ Account note — cost overrun HAC 04 Oct 2026 · 08:15
Splits install running over on labour (access delays from builder). Raise variation for standby time before next claim.
↗ RFI 022 — HAC-J2623 — Variation: additional FCU to comms room per tenant request HAC synced 15 Jul 2026 · 11:40
From Greg Pollard <gpollard@harveyind.com.au> · To Elias Daher <elias@edtprojects.com.au>
Hi Elias,
Variation: additional FCU to comms room per tenant request
Marked-up drawing attached.
Greg Pollard◷ Site coordination meeting — Lincoln Rise Stage 2 HAC 13 Jul 2026 · 07:30
Attendees: Elias Daher, Greg Pollard, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↙ RFI 019 — HAC-J2623 — BMS points list HAC synced 01 Jul 2026 · 13:07
From Elias Daher <elias@edtprojects.com.au> · To Greg Pollard <gpollard@harveyind.com.au>
Hi Greg,
BMS points list — confirm naming convention
Please advise by end of week.
Elias Daher◷ Site coordination meeting — Lincoln Rise Stage 2 HAC 29 Jun 2026 · 07:30
Attendees: Elias Daher, Greg Pollard, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↗ RFI 016 — HAC-J2623 — Confirm chilled beam supply temperature for L15 tenancy HAC synced 17 Jun 2026 · 15:25
From Greg Pollard <gpollard@harveyind.com.au> · To Elias Daher <elias@edtprojects.com.au>
Hi Elias,
Confirm chilled beam supply temperature for L15 tenancy
Marked-up drawing attached.
Greg Pollard◷ Site coordination meeting — Lincoln Rise Stage 2 HAC 15 Jun 2026 · 07:30
Attendees: Elias Daher, Greg Pollard, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↗ Re: Quotation HAC-Q2646 — Lincoln Rise Stage 2 — 64 apartments HAC synced 15 May 2026 · 16:26
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Elias Daher <elias@edtprojects.com.au>
Thanks Elias — appreciated. Greg Pollard will be your project manager and will be in touch this week.
Rowan Kennedy↙ Re: Quotation HAC-Q2646 — Lincoln Rise Stage 2 — 64 apartments HAC synced 15 May 2026 · 10:00
From Elias Daher <elias@edtprojects.com.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan,
Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule.
Elias Daher↗ Quotation HAC-Q2646 — Lincoln Rise Stage 2 — 64 apartments HAC sent 25 Apr 2026 · 17:31
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Elias Daher <elias@edtprojects.com.au>
Hi Elias,
Please find attached our quotation HAC-Q2646 for Lincoln Rise Stage 2 — 64 apartments — $812,000 + GST, valid 30 days.
Happy to walk through it.
Regards,
Rowan Kennedy