Commissioning report · HN-J0415

Wests New Lambton — stage 3 auditorium & dust-free kitchen
Demo 06 Oct 2026
← HN-J0415
8/12 checks passed
Harvey
Harveys Newcastle Pty Ltd · Harveys Newcastle
16 Parker St, Carrington NSW 2294 · (02) 4961 6261 · general@harveysnewcastle.com.au
ABN 63 000 792 638 · ARCtick AU
Commissioning report
HN-J0415
Date 06 Oct 2026
Stage Commissioning
Checks passed 8 of 12
Client
Western Suburbs Leagues Club Newcastle
Wests New Lambton — stage 3 auditorium & dust-free kitchen
Cnr Northcott Dr & Croudace St, New Lambton
AHU-AUD — Air handling unit Custom 6 kL/s
Installed to drawings & clearancesPassPeter Cox 20 Sep 2026
Pressure / leak test (refrigerant or CHW) (hold point)Held 1,000 kPa 2 hPassPeter Cox 17 Sep 2026
Electrical & controls checkedPassPeter Cox 08 Sep 2026
Airflow / capacity measured vs design (hold point)6,730 l/s (design 6,750)PassPeter Cox 22 Sep 2026
BMS points verifiedPending
Commissioned & signed off (hold point)Pending
KEF-W3 — Kitchen exhaust fan In-line Centrifugal 630 backward inclined · S/N FBA-26-0416
Installed to drawings, mounts & flex connectionsPassPeter Cox 03 Oct 2026
Rotation, alignment & vibration check1.2 mm/sPassPeter Cox 21 Sep 2026
Electrical, isolator & VSD set-upPassPeter Cox 02 Oct 2026
Airflow measured vs design (hold point)3,590 l/s (design 3,600)PassPeter Cox 29 Sep 2026
BMS points verifiedPending
Commissioned & signed off (hold point)Pending
Inspection & test plan per the Harvey quality system (AS 2990 / ISO 9001 based). Hold points witnessed before sign-off. Asset barcodes are issued at handover to Service.