← HN-J04158/12 checks passed
Harveys Newcastle Pty Ltd · Harveys Newcastle
16 Parker St, Carrington NSW 2294 · (02) 4961 6261 · general@harveysnewcastle.com.au
ABN 63 000 792 638 · ARCtick AU
Commissioning report
HN-J0415
Date 06 Oct 2026
Stage Commissioning
Checks passed 8 of 12
Client
Western Suburbs Leagues Club Newcastle
Wests New Lambton — stage 3 auditorium & dust-free kitchen
Cnr Northcott Dr & Croudace St, New Lambton
AHU-AUD — Air handling unit Custom 6 kL/s
| Installed to drawings & clearances | Pass | Peter Cox 20 Sep 2026 | |
| Pressure / leak test (refrigerant or CHW) (hold point) | Held 1,000 kPa 2 h | Pass | Peter Cox 17 Sep 2026 |
| Electrical & controls checked | Pass | Peter Cox 08 Sep 2026 | |
| Airflow / capacity measured vs design (hold point) | 6,730 l/s (design 6,750) | Pass | Peter Cox 22 Sep 2026 |
| BMS points verified | Pending | ||
| Commissioned & signed off (hold point) | Pending |
KEF-W3 — Kitchen exhaust fan In-line Centrifugal 630 backward inclined · S/N FBA-26-0416
| Installed to drawings, mounts & flex connections | Pass | Peter Cox 03 Oct 2026 | |
| Rotation, alignment & vibration check | 1.2 mm/s | Pass | Peter Cox 21 Sep 2026 |
| Electrical, isolator & VSD set-up | Pass | Peter Cox 02 Oct 2026 | |
| Airflow measured vs design (hold point) | 3,590 l/s (design 3,600) | Pass | Peter Cox 29 Sep 2026 |
| BMS points verified | Pending | ||
| Commissioned & signed off (hold point) | Pending |
Inspection & test plan per the Harvey quality system (AS 2990 / ISO 9001 based). Hold points witnessed before sign-off. Asset barcodes are issued at handover to Service.