Harvey

HN-J0412

University of Newcastle Medical Sciences — level 3 refurbishment · University of Newcastle
Demo 06 Oct 2026
← Contracts
1
Enquiry
direct order
✓
Quote
3
Jobin progress
✓
Invoices
5
Look after it
not yet
Next step
Order the 1 FBA fan
They go straight onto the Fan & Blower factory board as inter-company works orders; the cost comes back onto this job when they're dispatched.
ContractHarveys NewcastleRefurbishmentInstallationOn track
Client
University of Newcastle · Mark Hollis
Site
University Dr, Callaghan
Project manager
Gary Niass
Program
27 Aug 2026 → PC 23 Nov 2026
Scope
Lab supply & exhaust, FCUs, ductwork made at Carrington, BMS integration.
From quote
HN-QNaN
44% complete
MoneyForecast margin 23.1%
Contract value$468,000.00 Approved variations$18,700.00 Revised contract$486,700.00 Cost budget (from estimate)$397,100.00 Cost to date$151,659.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$374,035.00 Earned (44%)$214,148.00 Claimed to date$201,299.12 Retention held by client$10,064.96
Equipment $72,031 Site labour $39,872 Controls subcontract $13,011 Electrical subcontract $10,049 Cranage & rigging $6,714 Pipework & materials $9,982
Equipment schedule1 FBA fan line(s) · 1 not yet ordered
TagTypeMake / modelLocationkWSupplyFBA works orderSerial
FCU-L3 (×8) (×8) Fan coil unit OPA 450 FCU Level 3 0.4 Supplier — —
LEF-L3 Lab exhaust fan Series 1000 SWSI 560 aerofoil Roof 4 FBA Not ordered —
Inspection & test plan2/12 passed · 5 hold points openCommissioning report
FCU-L3 (×8)
Installed to drawings & clearances
Peter Cox · 12 Sep 2026
Pass
Pressure / leak test (refrigerant or CHW)hold
Electrical & controls checked
Airflow / capacity measured vs designhold
BMS points verified
Commissioned & signed offhold
LEF-L3
Installed to drawings, mounts & flex connections
Peter Cox · 30 Sep 2026
Pass
Rotation, alignment & vibration check
Electrical, isolator & VSD set-up
Airflow measured vs designhold
BMS points verified
Commissioned & signed offhold
Costs to date$151,659
DateCategoryDescriptionAmount
06 Oct 2026 Pipework & materials Pipework & materials — claim 2 $4,550
06 Oct 2026 Cranage & rigging Cranage & rigging — claim 2 $3,194
06 Oct 2026 Electrical subcontract Electrical subcontract — claim 2 $4,749
06 Oct 2026 Controls subcontract Controls subcontract — claim 2 $6,461
06 Oct 2026 Site labour Site labour — weeks 7–9 $12,242
06 Oct 2026 Equipment Supply — CRAC units $34,032
28 Sep 2026 Site labour Site labour — weeks 4–6 $12,519
16 Sep 2026 Pipework & materials Pipework & materials — claim 1 $5,432
16 Sep 2026 Cranage & rigging Cranage & rigging — claim 1 $3,520
16 Sep 2026 Electrical subcontract Electrical subcontract — claim 1 $5,300
16 Sep 2026 Controls subcontract Controls subcontract — claim 1 $6,550
16 Sep 2026 Equipment Supply — packaged units $37,999
11 Sep 2026 Site labour Site labour — weeks 1–3 $15,111
Emails & activity · 9
↗ RFI 031 — HN-J0412 — Access to plantroom for crane lift Gary Niass → Mark Hollis HAC synced 03 Oct 2026 · 11:43
From Gary Niass <gniass@harveysnewcastle.com.au> · To Mark Hollis <mark@newcastle.edu.au>
Hi Mark, Access to plantroom for crane lift — Saturday OK? Marked-up drawing attached. Gary Niass
◷ Site coordination meeting — University of Newcastle Medical Sciences Meeting · Mark Hollis · Gary Niass HAC 01 Oct 2026 · 07:30
Attendees: Mark Hollis, Gary Niass, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↙ RFI 028 — HN-J0412 — BMS points list Mark Hollis → Gary Niass HAC synced 19 Sep 2026 · 09:30
From Mark Hollis <mark@newcastle.edu.au> · To Gary Niass <gniass@harveysnewcastle.com.au>
Hi Gary, BMS points list — confirm naming convention Please advise by end of week. Mark Hollis
◷ Site coordination meeting — University of Newcastle Medical Sciences Meeting · Mark Hollis · Gary Niass HAC 17 Sep 2026 · 07:30
Attendees: Mark Hollis, Gary Niass, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↗ RFI 025 — HN-J0412 — BMS points list Gary Niass → Mark Hollis HAC synced 05 Sep 2026 · 12:10
From Gary Niass <gniass@harveysnewcastle.com.au> · To Mark Hollis <mark@newcastle.edu.au>
Hi Mark, BMS points list — confirm naming convention Marked-up drawing attached. Gary Niass
◷ Site coordination meeting — University of Newcastle Medical Sciences Meeting · Mark Hollis · Gary Niass HAC 03 Sep 2026 · 07:30
Attendees: Mark Hollis, Gary Niass, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↗ Re: Quotation HN-QNaN — University of Newcastle Medical Sciences — level 3 refurbishment Gary Niass → Mark Hollis HN synced 05 Aug 2026 · 16:41
From Gary Niass <gniass@harveysnewcastle.com.au> · To Mark Hollis <mark@newcastle.edu.au>
Thanks Mark — appreciated. We'll be in touch to book it in. Gary Niass
↙ Re: Quotation HN-QNaN — University of Newcastle Medical Sciences — level 3 refurbishment Mark Hollis → Gary Niass HN synced 05 Aug 2026 · 10:00
From Mark Hollis <mark@newcastle.edu.au> · To Gary Niass <gniass@harveysnewcastle.com.au>
Hi Gary, Approved — please proceed. Our order number to follow. Thanks, Mark Hollis
↗ Quotation HN-QNaN — University of Newcastle Medical Sciences — level 3 refurbishment Gary Niass → Mark Hollis HN sent 13 Jul 2026 · 16:28
From Gary Niass <gniass@harveysnewcastle.com.au> · To Mark Hollis <mark@newcastle.edu.au>
Hi Mark, Please find attached our quotation HN-QNaN for University of Newcastle Medical Sciences — level 3 refurbishment — $468,000 + GST, valid 30 days. Happy to walk through it. Regards, Gary Niass