Fox Hills Clubhouse — Six-monthly PPM — Split system (DA19 schedule)
Demo 06 Oct 2026
← Service calls
1
Enquiry
direct order
2
Quote
no quote
✓
Job
4
Invoicesnext
not yet
✓
Look after it
Status
Closed — covered by the maintenance agreement
✓
Logged
✓
Dispatched
✓
On site
✓
Completed
5
Invoiced
JobHarvey AirCon ServiceLowPPM
Customer
Fox Hills Golf Club
Site
Fox Hills Clubhouse
Prospect Hwy, Prospect NSW
Site contact
Darren Ellis · (02) 9610 4528
Access
Report to duty manager — after 10am only
Problem
Six-monthly PPM — Split system (DA19 schedule)
Logged
02 Oct 2026 · 12:20
Technician
Chris Mifsud · 02 Oct 2026
Asset
HA-004178 Split system Daikin FTXV — Level 1 — office 15
Agreement
MC-0146
Work done
Service completed to DA19 checklist. Filters changed, belts checked, coil cleaned. Barcode scanned. Covered under maintenance agreement.
Hours6 Labour$0.00 (agreement) Parts & materials$0.00 Completed02 Oct 2026 · 16:15
Assets at this site — scan each barcode on the visit
BarcodeAssetLocationFrequencyLast serviceNext due
HA-004175Split system Daikin FTXVRoom 16Six-monthly23 Mar 202621 Sep 2026
HA-004174Split system Daikin FTXVLevel 2 — office 2Six-monthly27 Mar 202625 Sep 2026
HA-004172Package unit Temperzone OPA 960Plant room 1Quarterly14 Jul 202613 Oct 2026
HA-004180Kitchen exhaust fan FBA ILC-560Plant deckQuarterly08 Aug 202607 Nov 2026
HA-004176Split system Daikin FTXVLevel 2 — office 6Six-monthly28 May 202626 Nov 2026
HA-004173Package unit Temperzone OPA 960Roof #2Quarterly04 Sep 202604 Dec 2026
HA-004177Split system Daikin FTXVMeeting room 19Six-monthly03 Jul 202601 Jan 2027
HA-004178Split system Daikin FTXVLevel 1 — office 15Six-monthly13 Sep 202614 Mar 2027
HA-004179Split system Daikin FTXVLevel 1 — office 2Six-monthly13 Sep 202614 Mar 2027
Harvey
Harvey Air Conditioning Pty Ltd · Harvey AirCon Service
Cnr Macarthur & Fennell Sts, Parramatta NSW 2150 · (02) 9630 5100 · service@harveyind.com.au
ABN 42 000 473 334 · ARCtick AU10031
Job sheet
SC-48138
Logged 02 Oct 2026 · 12:20
Urgency Low
Technician Chris Mifsud
Site
Fox Hills Clubhouse
Prospect Hwy, Prospect NSW
Fox Hills Golf Club
TypePPM
AssetHA-004178 Split system — Level 1 — office 15
Nature of problemSix-monthly PPM — Split system (DA19 schedule)
Work doneService completed to DA19 checklist. Filters changed, belts checked, coil cleaned. Barcode scanned. Covered under maintenance agreement.
Hours6