Harvey

HAC-Q2646

EDT Projects — Lincoln Rise Stage 2 — 64 apartments
Demo 06 Oct 2026
1
Enquiry
direct order
✓
Quote
3
Jobin progress
5
Look after it
not yet
Status
Accepted by Elias Daher — contract raised
Carry on from the job — it's linked above.
Linescost, sell and margin per line — totals recalculate as you edit
TypeDescriptionQtyUnit sellTotalMargin
DesignMechanical design, 3D drafting & shop drawings1$38,626.00$38,626.0020.0%
EquipmentMechanical plant & equipment (per schedule)1$278,107.00$278,107.0016.7%
FanFBA Series 1000 DWDI 800 aerofoil — CPS-01 Carpark supply fan1$22,490.00$22,490.0014.8%
FanFBA Series 1000 SWSI 800 aerofoil — CPE-01 Carpark exhaust fan1$16,990.00$16,990.0014.8%
DuctworkDuctwork manufacture (Parramatta) & install1$131,328.00$131,328.0023.5%
LabourSite installation labour & supervision1$193,130.00$193,130.0020.0%
SubcontractBMS / controls & electrical1$92,702.00$92,702.0016.7%
CommissioningTesting, balancing & commissioning, O&M manuals1$38,627.00$38,627.0020.0%
Harvey Air ConditioningAccepted
Customer
EDT Projects
Prepared by
Rowan Kennedy
Issued
25 Apr 2026
Valid until
25 May 2026
Accepted
15 May 2026 · 10:00 · Elias Daher
Cost$659,386.82 Sell (ex GST)$812,000.00 GST$81,200.00 Total inc GST$893,200.00
Margin 18.8% $152,613
Harvey
Harvey Air Conditioning Pty Ltd · Harvey Air Conditioning
Cnr Macarthur & Fennell Sts, Parramatta NSW 2150 · (02) 9630 5100 · air@harveyind.com.au
ABN 42 000 473 334 · ARCtick AU10031
Quotation
HAC-Q2646
Date 25 Apr 2026
Valid until 25 May 2026
Prepared by Rowan Kennedy
Quotation to
EDT Projects
Attn: Elias Daher
elias@edtprojects.com.au
Castle Hill NSW
ABN 92 153 040 817
For
Lincoln Rise Stage 2 — 64 apartments
16–20 Withers Rd, Kellyville
DescriptionQtyUnitAmount
Mechanical design, 3D drafting & shop drawings1$38,626.00$38,626.00
Mechanical plant & equipment (per schedule)1$278,107.00$278,107.00
FBA Series 1000 DWDI 800 aerofoil — CPS-01 Carpark supply fan1$22,490.00$22,490.00
FBA Series 1000 SWSI 800 aerofoil — CPE-01 Carpark exhaust fan1$16,990.00$16,990.00
Ductwork manufacture (Parramatta) & install1$131,328.00$131,328.00
Site installation labour & supervision1$193,130.00$193,130.00
BMS / controls & electrical1$92,702.00$92,702.00
Testing, balancing & commissioning, O&M manuals1$38,627.00$38,627.00
Subtotal (ex GST)$812,000.00
GST 10%$81,200.00
Total (inc GST)$893,200.00
Prices in AUD, GST shown separately. Valid 30 days. Subject to Harvey Air Conditioning standard terms of contract.
A member of the Harvey group of companies · Established 1895
Emails & activity · 3
↗ Re: Quotation HAC-Q2646 — Lincoln Rise Stage 2 — 64 apartments Rowan Kennedy → Elias Daher HAC synced 15 May 2026 · 16:26
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Elias Daher <elias@edtprojects.com.au>
Thanks Elias — appreciated. Greg Pollard will be your project manager and will be in touch this week. Rowan Kennedy
↙ Re: Quotation HAC-Q2646 — Lincoln Rise Stage 2 — 64 apartments Elias Daher → Rowan Kennedy HAC synced 15 May 2026 · 10:00
From Elias Daher <elias@edtprojects.com.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan, Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule. Elias Daher
↗ Quotation HAC-Q2646 — Lincoln Rise Stage 2 — 64 apartments Rowan Kennedy → Elias Daher HAC sent 25 Apr 2026 · 17:31
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Elias Daher <elias@edtprojects.com.au>
Hi Elias, Please find attached our quotation HAC-Q2646 for Lincoln Rise Stage 2 — 64 apartments — $812,000 + GST, valid 30 days. Happy to walk through it. Regards, Rowan Kennedy