Harvey

MC-0141

Fairfield Leisure Centre — Fairfield City Council
Demo 06 Oct 2026
← Maintenance
1
Enquiry
—
2
Quotenext
not yet
3
Job
not yet
✓
Invoices
✓
Look after it
Status
PPM visit booked
It's on the Service board — the asset dates roll forward when the visit is completed.
AgreementHarvey AirCon ServiceActive
Site
Fairfield Leisure Centre
Vine St, Fairfield NSW
Customer
Fairfield City Council · Robert Gauci
Term
19 Sep 2024 → 19 Sep 2026
Value
$48,600 a year · billed quarterly
Scope
PPM + essential services testing (AS 1851 fire mode)
Asset register — 10 assetsbarcode scanned at each service
BarcodeAssetMakeModelSerialLocationDA19 frequencyLast serviceNext due
HA-004107 Split system Daikin FTXM60 3598175 Level 2 — office 6 Six-monthly 16 Apr 2026 15 Oct 2026 Scheduled
HA-004102 AHU Harvey custom AHU 2840511 Roof #2 Quarterly 23 Jul 2026 22 Oct 2026 Scheduled
HA-004101 AHU Harvey custom AHU 4962849 Roof #1 Quarterly 26 Jul 2026 25 Oct 2026 Scheduled
HA-004103 AHU Harvey custom AHU 8644346 Mezzanine #3 Quarterly 31 Jul 2026 30 Oct 2026 Scheduled
HA-004100 Chiller Carrier 30RB-262 8569760 Plantroom Monthly 03 Oct 2026 02 Nov 2026 Scheduled
HA-004109 Split system Daikin FTXM60 1801195 Meeting room 18 Six-monthly 20 Jun 2026 19 Dec 2026 Scheduled
HA-004105 Pool hall exhaust fan FBA S1000-SWSI-800-AL FBA-19-0492 Roof — north #2 Six-monthly 19 Jul 2026 17 Jan 2027 Scheduled
HA-004106 Split system Daikin FTXM60 8984705 Level 2 — office 11 Six-monthly 29 Jul 2026 27 Jan 2027 Scheduled
HA-004108 Split system Daikin FTXM60 1949695 Meeting room 18 Six-monthly 08 Sep 2026 09 Mar 2027 Scheduled
HA-004104 Pool hall exhaust fan FBA S1000-SWSI-800-AL FBA-20-0317 Roof — north #1 Six-monthly 16 Sep 2026 17 Mar 2027 Scheduled