1
Enquiry
direct order
✓
Quote
3
Jobin progress
✓
Invoices
5
Look after it
not yet
Next step
Waiting for payment — due 31 Oct 2026
Mark it paid when it shows in the bank.
Harvey Air Conditioning Pty Ltd · Harvey Air Conditioning
Cnr Macarthur & Fennell Sts, Parramatta NSW 2150 · (02) 9630 5100 · air@harveyind.com.au
ABN 42 000 473 334 · ARCtick AU10031
Tax invoice
HAC-58225
Date 25 Sep 2026
Due 31 Oct 2026
Your order HAC-J2625
Bill to
Macquarie University
Attn: Owen Fitzgerald
owen@mq.edu.au
Macquarie Park NSW
ABN 48 367 236 976
Re
Progress claim 1 — Macquarie University Building 12 — chiller replacementHAC-J2625
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Progress claim 1: work completed to date 9% | 1 | $147,601.62 | $147,601.62 |
| Less retention 5% | 1 | −$7,380.08 | −$7,380.08 |
| Subtotal (ex GST) | $140,221.54 |
| GST 10% | $14,022.15 |
| Total (inc GST) | $154,243.69 |
Payment — EFT to Harvey Air Conditioning Pty Ltd, Westpac — Parramatta, BSB 032-078, Acct 41 6228. Please quote HAC-58225 as the reference.
Emails & activity · 5
↙ RFI 020 — HAC-J2625 — Fire mode testing date with certifier HAC synced 30 Sep 2026 · 09:46
From Owen Fitzgerald <owen@mq.edu.au> · To Greg Pollard <gpollard@harveyind.com.au>
Hi Greg,
Fire mode testing date with certifier
Please advise by end of week.
Owen Fitzgerald◷ Site coordination meeting — Macquarie University Building 12 HAC 28 Sep 2026 · 07:30
Attendees: Owen Fitzgerald, Greg Pollard, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↗ Tax invoice HAC-58225 — Progress claim 1 — Macquarie University Building 12 — chiller replacement HAC sent 25 Sep 2026 · 15:13
From Karen Mills <kmills@harveyind.com.au> · To Accounts Payable <accounts@mq.edu.au>
Hi,
Please find attached tax invoice HAC-58225 for $154,243.69 inc GST, due 31/10/2026.
Karen Mills
Accounts — Harvey Industries↗ RFI 017 — HAC-J2625 — Variation: additional FCU to comms room per tenant request HAC synced 16 Sep 2026 · 14:25
From Greg Pollard <gpollard@harveyind.com.au> · To Owen Fitzgerald <owen@mq.edu.au>
Hi Owen,
Variation: additional FCU to comms room per tenant request
Marked-up drawing attached.
Greg Pollard◷ Site coordination meeting — Macquarie University Building 12 HAC 14 Sep 2026 · 07:30
Attendees: Owen Fitzgerald, Greg Pollard, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.