1
Enquiry
direct order
✓
Quote
5
Look after it
not yet
Status
Paid 23 Jul 2026
Harvey Air Conditioning Pty Ltd · Harvey Air Conditioning
Cnr Macarthur & Fennell Sts, Parramatta NSW 2150 · (02) 9630 5100 · air@harveyind.com.au
ABN 42 000 473 334 · ARCtick AU10031
Tax invoice
HAC-58214
Date 25 Jun 2026
Due 31 Jul 2026
Your order HAC-J2614
Bill to
Westmead Institute for Medical Research
Attn: Dr. Helen Ruiz
dr@westmeadinstitute.org.au
Westmead NSW
ABN 27 355 485 230
Re
Progress claim 2 — Westmead Institute — Level 3 PC2 laboratoriesHAC-J2614
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Progress claim 2: work completed to date 32% | 1 | $127,512.86 | $127,512.86 |
| Less retention 5% | 1 | −$6,375.64 | −$6,375.64 |
| Subtotal (ex GST) | $121,137.22 |
| GST 10% | $12,113.72 |
| Total (inc GST) | $133,250.94 |
Payment — EFT to Harvey Air Conditioning Pty Ltd, Westpac — Parramatta, BSB 032-078, Acct 41 6228. Please quote HAC-58214 as the reference.
PAID 23 Jul 2026 — thank you.
Emails & activity · 7
↗ Tax invoice HAC-58214 — Progress claim 2 — Westmead Institute — Level 3 PC2 laboratories HAC sent 25 Jun 2026 · 17:08
From Karen Mills <kmills@harveyind.com.au> · To Accounts Payable <accounts@westmeadinstitute.org.au>
Hi,
Please find attached tax invoice HAC-58214 for $133,250.94 inc GST, due 31/07/2026.
Karen Mills
Accounts — Harvey Industries↗ RFI 018 — HAC-J2614 — Fire mode testing date with certifier HAC synced 24 Jun 2026 · 10:21
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Dr. Helen Ruiz <dr@westmeadinstitute.org.au>
Hi Helen,
Fire mode testing date with certifier
Marked-up drawing attached.
Matt Corrigan◷ Site coordination meeting — Westmead Institute HAC 22 Jun 2026 · 07:30
Attendees: Dr. Helen Ruiz, Matt Corrigan, Luke Brennan. Commissioning dates agreed with BMS subcontractor.
↙ RFI 015 — HAC-J2614 — Ceiling void clash with sprinkler main on grid C HAC synced 10 Jun 2026 · 09:20
From Dr. Helen Ruiz <dr@westmeadinstitute.org.au> · To Matt Corrigan <mcorrigan@harveyind.com.au>
Hi Matt,
Ceiling void clash with sprinkler main on grid C — can ductwork drop 150mm?
Please advise by end of week.
Dr. Helen Ruiz◷ Site coordination meeting — Westmead Institute HAC 08 Jun 2026 · 07:30
Attendees: Dr. Helen Ruiz, Matt Corrigan, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↗ RFI 012 — HAC-J2614 — Variation: additional FCU to comms room per tenant request HAC synced 27 May 2026 · 10:02
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Dr. Helen Ruiz <dr@westmeadinstitute.org.au>
Hi Helen,
Variation: additional FCU to comms room per tenant request
Marked-up drawing attached.
Matt Corrigan◷ Site coordination meeting — Westmead Institute HAC 25 May 2026 · 07:30
Attendees: Dr. Helen Ruiz, Matt Corrigan, Luke Brennan. Commissioning dates agreed with BMS subcontractor.