Raise this month's progress claim — $10,720 to claim
Work done to date 4% ($10,720); claimed so far $0. Retention 5% is held automatically.
ContractDesign & DraftingOn track
- Client
- Jones Lang LaSalle · Priya Raman
- Site
- 201 Kent St, Sydney
- Project manager
- Greg Pollard
- Program
- 19 Oct 2026 → PC 11 Jan 2027
- Scope
- VAV fitout off base building, supplementary DX to comms room, BMS integration.
- From quote
- HAC-Q2644
4% complete
MoneyForecast margin 17.5%
Contract value$268,000.00 Approved variations$0.00 Revised contract$268,000.00 Cost budget (from estimate)$221,600.00 Cost to date$8,274.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$221,010.00 Earned (4%)$10,720.00 Claimed to date$0.00 Retention held by client$0.00
Equipment $3,162 Ductwork (Parramatta shop) $1,420 Site labour $2,055 Controls subcontract $616 Electrical subcontract $509 Pipework & materials $512
Equipment schedule0 FBA fan line(s) · 0 not yet ordered
| Tag | Type | Make / model | Location | kW | Supply | FBA works order | Serial |
|---|
Nothing here yet — use “Add equipment” to create the first one.
Costs to date$8,274
| Date | Category | Description | Amount | |
|---|---|---|---|---|
| 06 Oct 2026 | Pipework & materials | Pipework & materials — claim 2 | $242 | |
| 06 Oct 2026 | Pipework & materials | Pipework & materials — claim 1 | $270 | |
| 06 Oct 2026 | Electrical subcontract | Electrical subcontract — claim 2 | $249 | |
| 06 Oct 2026 | Electrical subcontract | Electrical subcontract — claim 1 | $260 | |
| 06 Oct 2026 | Controls subcontract | Controls subcontract — claim 2 | $322 | |
| 06 Oct 2026 | Controls subcontract | Controls subcontract — claim 1 | $294 | |
| 06 Oct 2026 | Site labour | Site labour — weeks 7–9 | $664 | |
| 06 Oct 2026 | Site labour | Site labour — weeks 4–6 | $721 | |
| 06 Oct 2026 | Site labour | Site labour — weeks 1–3 | $670 | |
| 06 Oct 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 3 | $432 | |
| 06 Oct 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 2 | $473 | |
| 06 Oct 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 1 | $515 | |
| 06 Oct 2026 | Equipment | Progress claim — FCUs | $1,629 | |
| 06 Oct 2026 | Equipment | Supply — FCUs | $1,533 | |
Progress claims0 issued
No claims yet — set % complete, then “Progress claim”.
Emails & activity · 3
↗ Re: Quotation HAC-Q2644 — 201 Kent St — Level 22 tenancy HAC synced 26 Sep 2026 · 16:12
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Priya Raman <priya@jll.com>
Thanks Priya — appreciated. Greg Pollard will be your project manager and will be in touch this week.
Rowan Kennedy↙ Re: Quotation HAC-Q2644 — 201 Kent St — Level 22 tenancy HAC synced 26 Sep 2026 · 10:00
From Priya Raman <priya@jll.com> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan,
Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule.
Priya Raman↗ Quotation HAC-Q2644 — 201 Kent St — Level 22 tenancy HAC sent 07 Sep 2026 · 17:35
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Priya Raman <priya@jll.com>
Hi Priya,
Please find attached our quotation HAC-Q2644 for 201 Kent St — Level 22 tenancy — $268,000 + GST, valid 30 days.
Happy to walk through it.
Regards,
Rowan Kennedy