Harvey

HAC-J2614

Westmead Institute — Level 3 PC2 laboratories · Westmead Institute for Medical Research
Demo 06 Oct 2026
← Contracts
✓
Quote accepted
HAC-Q2642
✓
Contract
Commissioning
✓
FBA fans
2/2 delivered
4
Practical completion
12 Oct 2026
5
Service handover
pending
ContractCommissioningWatch
Client
Westmead Institute for Medical Research · Dr. Helen Ruiz
Site
176 Hawkesbury Rd, Westmead
Project manager
Matt Corrigan
Program
18 May 2026 → PC 12 Oct 2026
Scope
Lab supply & exhaust, fume cupboard exhaust fans (FBA), pressure cascade, BMS.
From quote
HAC-Q2642
91% complete
MoneyForecast margin 16.4%
Contract value$742,000.00 Approved variations$36,300.00 Revised contract$778,300.00 Cost budget (from estimate)$639,200.00 Cost to date$592,979.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$650,507.00 Earned (91%)$708,253.00 Claimed to date$665,757.82 Retention held by client$33,287.89
Equipment $205,090 FBA fans (inter-company) $11,046 Ductwork (Parramatta shop) $87,260 Site labour $142,807 Controls subcontract $48,081 Electrical subcontract $35,350 Cranage & rigging $23,500 Pipework & materials $39,845
Equipment schedule2 FBA fan line(s) · 0 not yet ordered
TagTypeMake / modelLocationkWSupplyFBA works orderSerial
FEF-01 Fume cupboard exhaust Series 1000 SWSI 500 aerofoil Roof 4 FBA WO-26116 · Dispatched FBA-26-0408
FEF-02 Fume cupboard exhaust Series 1000 SWSI 500 aerofoil Roof 4 FBA WO-26117 · Dispatched FBA-26-0409
AHU-L3 Lab AHU (100% OA) AHU 12 kL/s Level 3 plant 11 Supplier — —
Costs to date$592,979
DateCategoryDescriptionAmount
27 Aug 2026 FBA fans (inter-company) WO-26117 Series 1000 SWSI 500 aerofoil — FEF-02 Fume cupboard exhaust $5,523
27 Aug 2026 FBA fans (inter-company) WO-26116 Series 1000 SWSI 500 aerofoil — FEF-01 Fume cupboard exhaust $5,523
02 Jul 2026 Site labour Site labour — weeks 7–9 $41,820
02 Jul 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 3 $28,958
29 Jun 2026 Pipework & materials Pipework & materials — claim 2 $19,299
29 Jun 2026 Cranage & rigging Cranage & rigging — claim 2 $12,737
29 Jun 2026 Electrical subcontract Electrical subcontract — claim 2 $19,866
29 Jun 2026 Controls subcontract Controls subcontract — claim 2 $21,647
29 Jun 2026 Equipment Delivery — packaged units $107,438
17 Jun 2026 Site labour Site labour — weeks 4–6 $47,010
17 Jun 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 2 $30,069
08 Jun 2026 Pipework & materials Pipework & materials — claim 1 $20,546
08 Jun 2026 Cranage & rigging Cranage & rigging — claim 1 $10,763
08 Jun 2026 Electrical subcontract Electrical subcontract — claim 1 $15,484
08 Jun 2026 Controls subcontract Controls subcontract — claim 1 $26,434
08 Jun 2026 Equipment Supply — CRAC units $97,652
02 Jun 2026 Site labour Site labour — weeks 1–3 $53,977
02 Jun 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 1 $28,233
Emails & activity · 9
↗ RFI 018 — HAC-J2614 — Fire mode testing date with certifier Matt Corrigan → Dr. Helen Ruiz HAC synced 24 Jun 2026 · 10:21
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Dr. Helen Ruiz <dr@westmeadinstitute.org.au>
Hi Helen, Fire mode testing date with certifier Marked-up drawing attached. Matt Corrigan
◷ Site coordination meeting — Westmead Institute Meeting · Dr. Helen Ruiz · Matt Corrigan HAC 22 Jun 2026 · 07:30
Attendees: Dr. Helen Ruiz, Matt Corrigan, Luke Brennan. Commissioning dates agreed with BMS subcontractor.
↙ RFI 015 — HAC-J2614 — Ceiling void clash with sprinkler main on grid C Dr. Helen Ruiz → Matt Corrigan HAC synced 10 Jun 2026 · 09:20
From Dr. Helen Ruiz <dr@westmeadinstitute.org.au> · To Matt Corrigan <mcorrigan@harveyind.com.au>
Hi Matt, Ceiling void clash with sprinkler main on grid C — can ductwork drop 150mm? Please advise by end of week. Dr. Helen Ruiz
◷ Site coordination meeting — Westmead Institute Meeting · Dr. Helen Ruiz · Matt Corrigan HAC 08 Jun 2026 · 07:30
Attendees: Dr. Helen Ruiz, Matt Corrigan, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↗ RFI 012 — HAC-J2614 — Variation: additional FCU to comms room per tenant request Matt Corrigan → Dr. Helen Ruiz HAC synced 27 May 2026 · 10:02
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Dr. Helen Ruiz <dr@westmeadinstitute.org.au>
Hi Helen, Variation: additional FCU to comms room per tenant request Marked-up drawing attached. Matt Corrigan
◷ Site coordination meeting — Westmead Institute Meeting · Dr. Helen Ruiz · Matt Corrigan HAC 25 May 2026 · 07:30
Attendees: Dr. Helen Ruiz, Matt Corrigan, Luke Brennan. Commissioning dates agreed with BMS subcontractor.
↗ Re: Quotation HAC-Q2642 — Westmead Institute — Level 3 PC2 laboratories Rowan Kennedy → Dr. Helen Ruiz HAC synced 24 Apr 2026 · 16:25
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Dr. Helen Ruiz <dr@westmeadinstitute.org.au>
Thanks Helen — appreciated. Greg Pollard will be your project manager and will be in touch this week. Rowan Kennedy
↙ Re: Quotation HAC-Q2642 — Westmead Institute — Level 3 PC2 laboratories Dr. Helen Ruiz → Rowan Kennedy HAC synced 24 Apr 2026 · 10:00
From Dr. Helen Ruiz <dr@westmeadinstitute.org.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan, Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule. Dr. Helen Ruiz
↗ Quotation HAC-Q2642 — Westmead Institute — Level 3 PC2 laboratories Rowan Kennedy → Dr. Helen Ruiz HAC sent 22 Mar 2026 · 16:19
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Dr. Helen Ruiz <dr@westmeadinstitute.org.au>
Hi Helen, Please find attached our quotation HAC-Q2642 for Westmead Institute — Level 3 PC2 laboratories — $742,000 + GST, valid 30 days. Happy to walk through it. Regards, Rowan Kennedy