Harvey

HN-J0415

Wests New Lambton — stage 3 auditorium & dust-free kitchen · Western Suburbs Leagues Club Newcastle
Demo 06 Oct 2026
← Contracts
1
Enquiry
direct order
✓
Quote
✓
Invoices
5
Look after it
not yet
Next step
Finish commissioning — 4 ITP checks outstanding
2 hold points still open. Tick each check below as it's witnessed; then move the contract to Practical Completion.
ContractHarveys NewcastleDesign & constructCommissioningOn track
Client
Western Suburbs Leagues Club Newcastle · Glenn Hartley
Site
Cnr Northcott Dr & Croudace St, New Lambton
Project manager
Peter Cox
Program
10 Jul 2026 → PC 16 Oct 2026
Scope
Auditorium AHU, kitchen exhaust (FBA in-line), make-up air, grease-duct fabrication.
From quote
HN-QNaN
90% complete
MoneyForecast margin 24.7%
Contract value$352,000.00 Approved variations$8,800.00 Revised contract$360,800.00 Cost budget (from estimate)$298,900.00 Cost to date$241,766.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$271,656.00 Earned (90%)$324,720.00 Claimed to date$305,236.80 Retention held by client$15,261.84
Equipment $105,055 FBA fans (inter-company) $6,714 Ductwork (Carrington shop) $10,246 Site labour $60,139 Controls subcontract $19,846 Electrical subcontract $14,800 Cranage & rigging $10,544 Pipework & materials $14,422
Equipment schedule1 FBA fan line(s) · 0 not yet ordered
TagTypeMake / modelLocationkWSupplyFBA works orderSerial
AHU-AUD Air handling unit Custom 6 kL/s Auditorium plant 7.5 Supplier — —
KEF-W3 Kitchen exhaust fan In-line Centrifugal 630 backward inclined Roof 4 FBA WO-26127 · Dispatched FBA-26-0416
Inspection & test plan8/12 passed · 2 hold points openCommissioning report
AHU-AUD
Installed to drawings & clearances
Peter Cox · 20 Sep 2026
Pass
Pressure / leak test (refrigerant or CHW)hold
Held 1,000 kPa 2 h
Peter Cox · 17 Sep 2026
Pass
Electrical & controls checked
Peter Cox · 08 Sep 2026
Pass
Airflow / capacity measured vs designhold
6,730 l/s (design 6,750)
Peter Cox · 22 Sep 2026
Pass
BMS points verified
Commissioned & signed offhold
KEF-W3
Installed to drawings, mounts & flex connections
Peter Cox · 03 Oct 2026
Pass
Rotation, alignment & vibration check
1.2 mm/s
Peter Cox · 21 Sep 2026
Pass
Electrical, isolator & VSD set-up
Peter Cox · 02 Oct 2026
Pass
Airflow measured vs designhold
3,590 l/s (design 3,600)
Peter Cox · 29 Sep 2026
Pass
BMS points verified
Commissioned & signed offhold
Costs to date$241,766
DateCategoryDescriptionAmount
07 Sep 2026 FBA fans (inter-company) WO-26127 In-line Centrifugal 630 backward inclined — KEF-W3 Kitchen exhaust fan $6,714
24 Aug 2026 Site labour Site labour — weeks 7–9 $21,991
19 Aug 2026 Pipework & materials Pipework & materials — claim 2 $6,591
19 Aug 2026 Cranage & rigging Cranage & rigging — claim 2 $5,134
19 Aug 2026 Electrical subcontract Electrical subcontract — claim 2 $7,994
19 Aug 2026 Controls subcontract Controls subcontract — claim 2 $11,042
19 Aug 2026 Equipment Delivery — chiller deposit $55,740
10 Aug 2026 Site labour Site labour — weeks 4–6 $20,472
30 Jul 2026 Pipework & materials Pipework & materials — claim 1 $7,831
30 Jul 2026 Cranage & rigging Cranage & rigging — claim 1 $5,410
30 Jul 2026 Electrical subcontract Electrical subcontract — claim 1 $6,806
30 Jul 2026 Controls subcontract Controls subcontract — claim 1 $8,804
30 Jul 2026 Equipment Progress claim — condensers $49,315
27 Jul 2026 Site labour Site labour — weeks 1–3 $17,676
18 Jul 2026 Ductwork (Carrington shop) HNF-2623 Auditorium supply & return — 230 m² galvanised sheet $10,246
Emails & activity · 9
↗ RFI 032 — HN-J0415 — Access to plantroom for crane lift Peter Cox → Glenn Hartley HAC synced 16 Aug 2026 · 09:03
From Peter Cox <pcox@harveysnewcastle.com.au> · To Glenn Hartley <glenn@wests.com.au>
Hi Glenn, Access to plantroom for crane lift — Saturday OK? Marked-up drawing attached. Peter Cox
◷ Site coordination meeting — Wests New Lambton Meeting · Glenn Hartley · Peter Cox HAC 14 Aug 2026 · 07:30
Attendees: Glenn Hartley, Peter Cox, Luke Brennan. Commissioning dates agreed with BMS subcontractor.
↙ RFI 029 — HN-J0415 — Variation: additional FCU to comms room per tenant request Glenn Hartley → Peter Cox HAC synced 02 Aug 2026 · 10:13
From Glenn Hartley <glenn@wests.com.au> · To Peter Cox <pcox@harveysnewcastle.com.au>
Hi Peter, Variation: additional FCU to comms room per tenant request Please advise by end of week. Glenn Hartley
◷ Site coordination meeting — Wests New Lambton Meeting · Glenn Hartley · Peter Cox HAC 31 Jul 2026 · 07:30
Attendees: Glenn Hartley, Peter Cox, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↗ RFI 026 — HN-J0415 — Confirm chilled beam supply temperature for L15 tenancy Peter Cox → Glenn Hartley HAC synced 19 Jul 2026 · 15:18
From Peter Cox <pcox@harveysnewcastle.com.au> · To Glenn Hartley <glenn@wests.com.au>
Hi Glenn, Confirm chilled beam supply temperature for L15 tenancy Marked-up drawing attached. Peter Cox
◷ Site coordination meeting — Wests New Lambton Meeting · Glenn Hartley · Peter Cox HAC 17 Jul 2026 · 07:30
Attendees: Glenn Hartley, Peter Cox, Luke Brennan. Plant delivery confirmed for crane lift; road closure permit lodged.
↗ Re: Quotation HN-QNaN — Wests New Lambton — stage 3 auditorium & dust-free kitchen Gary Niass → Glenn Hartley HN synced 11 Jun 2026 · 16:34
From Gary Niass <gniass@harveysnewcastle.com.au> · To Glenn Hartley <glenn@wests.com.au>
Thanks Glenn — appreciated. We'll be in touch to book it in. Gary Niass
↙ Re: Quotation HN-QNaN — Wests New Lambton — stage 3 auditorium & dust-free kitchen Glenn Hartley → Gary Niass HN synced 11 Jun 2026 · 10:00
From Glenn Hartley <glenn@wests.com.au> · To Gary Niass <gniass@harveysnewcastle.com.au>
Hi Gary, Approved — please proceed. Our order number to follow. Thanks, Glenn Hartley
↗ Quotation HN-QNaN — Wests New Lambton — stage 3 auditorium & dust-free kitchen Gary Niass → Glenn Hartley HN sent 21 May 2026 · 14:29
From Gary Niass <gniass@harveysnewcastle.com.au> · To Glenn Hartley <glenn@wests.com.au>
Hi Glenn, Please find attached our quotation HN-QNaN for Wests New Lambton — stage 3 auditorium & dust-free kitchen — $352,000 + GST, valid 30 days. Happy to walk through it. Regards, Gary Niass