Next step
Order the 2 FBA fans
They go straight onto the Fan & Blower factory board as inter-company works orders; the cost comes back onto this job when they're dispatched.
ContractDesign & DraftingOn track
- Client
- Fairfield City Council · Robert Gauci
- Site
- Vine St, Fairfield
- Project manager
- Matt Corrigan
- Program
- 27 Oct 2026 → PC 25 Jan 2027
- Scope
- Pool hall dehumidification, corrosion-protected supply & exhaust (FBA, epoxy finish).
- From quote
- HAC-Q2652
2% complete
MoneyForecast margin 17.7%
Contract value$356,000.00 Approved variations$0.00 Revised contract$356,000.00 Cost budget (from estimate)$294,700.00 Cost to date$4,258.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$293,064.00 Earned (2%)$7,120.00 Claimed to date$0.00 Retention held by client$0.00
Equipment $1,927 Ductwork (Parramatta shop) $889 Site labour $1,442
Equipment schedule2 FBA fan line(s) · 2 not yet ordered
| Tag | Type | Make / model | Location | kW | Supply | FBA works order | Serial | |
|---|---|---|---|---|---|---|---|---|
| PHS-1 | Pool hall supply fan (epoxy) | Series 1000 DWDI 800 aerofoil | Plant room | 11 | FBA | Not ordered | — | |
| PHE-1 | Pool hall exhaust fan (epoxy) | Series 1000 SWSI 800 aerofoil | Roof | 7.5 | FBA | Not ordered | — | |
Costs to date$4,258
| Date | Category | Description | Amount | |
|---|---|---|---|---|
| 06 Oct 2026 | Site labour | Site labour — weeks 7–9 | $448 | |
| 06 Oct 2026 | Site labour | Site labour — weeks 4–6 | $491 | |
| 06 Oct 2026 | Site labour | Site labour — weeks 1–3 | $503 | |
| 06 Oct 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 3 | $271 | |
| 06 Oct 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 2 | $291 | |
| 06 Oct 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 1 | $327 | |
| 06 Oct 2026 | Equipment | Delivery — VSDs | $1,023 | |
| 06 Oct 2026 | Equipment | Progress claim — CRAC units | $904 | |
Progress claims0 issued
No claims yet — set % complete, then “Progress claim”.
Emails & activity · 2
↗ Re: Quotation HAC-Q2652 — Fairfield Leisure Centre — pool hall ventilation HAC synced 06 Oct 2026 · 09:23
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Robert Gauci <robert@fairfieldcity.nsw.gov.au>
Thanks Robert — appreciated. Greg Pollard will be your project manager and will be in touch this week.
Rowan Kennedy↗ Quotation HAC-Q2652 — Fairfield Leisure Centre — pool hall ventilation HAC sent 25 Aug 2026 · 17:59
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Robert Gauci <robert@fairfieldcity.nsw.gov.au>
Hi Robert,
Please find attached our quotation HAC-Q2652 for Fairfield Leisure Centre — pool hall ventilation — $356,000 + GST, valid 30 days.
Happy to walk through it.
Regards,
Rowan Kennedy