Harvey

HAC-J2631

Rhodes Corporate Park Building C — base building upgrade · Investa Property Group
Demo 06 Oct 2026
← Contracts
✓
Quote accepted
HAC-Q2651
✓
Contract
Installation
3
FBA fans
0/4 delivered
4
Practical completion
27 Nov 2026
5
Service handover
pending
ContractInstallationOn track
Client
Investa Property Group · Tom Delaney
Site
1 Homebush Bay Dr, Rhodes
Project manager
Greg Pollard
Program
03 Aug 2026 → PC 27 Nov 2026
Scope
Replace AHU supply fans with FBA DWDI, new OA & toilet exhaust fans, chilled water pumps, BMS upgrade — building occupied.
From quote
HAC-Q2651
38% complete
MoneyForecast margin 16.2%
Contract value$1,394,000.00 Approved variations$42,000.00 Revised contract$1,436,000.00 Cost budget (from estimate)$1,191,000.00 Cost to date$464,904.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$1,203,324.00 Earned (38%)$545,680.00 Claimed to date$512,939.20 Retention held by client$25,646.96
Equipment $173,346 Ductwork (Parramatta shop) $76,469 Site labour $108,666 Controls subcontract $36,316 Electrical subcontract $24,367 Cranage & rigging $19,313 Pipework & materials $26,427
Equipment schedule4 FBA fan line(s) · 4 not yet ordered
TagTypeMake / modelLocationkWSupplyFBA works orderSerial
SF-C1 AHU supply fan Series 1000 DWDI 900 aerofoil AHU-C1 L1 plant 18.5 FBA Not ordered —
SF-C2 AHU supply fan Series 1000 DWDI 900 aerofoil AHU-C2 L6 plant 18.5 FBA Not ordered —
OAF-C1 Outside air fan Series 1000 SWSI 630 aerofoil Roof 5.5 FBA Not ordered —
TEF-C1 Toilet exhaust fan In-line Centrifugal 500 backward inclined Roof 2.2 FBA Not ordered —
CHWP-1/2 (×2) Chilled water pump NBE 100-250 Basement plant 15 Supplier — —
AHU-C1 Air handling unit (refurb) Refurbished casing + coil L1 plant 0 Supplier — —
AHU-C2 Air handling unit (refurb) Refurbished casing + coil L6 plant 0 Supplier — —
Costs to date$464,904
DateCategoryDescriptionAmount
17 Sep 2026 Site labour Site labour — weeks 7–9 $33,631
17 Sep 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 3 $26,138
14 Sep 2026 Pipework & materials Pipework & materials — claim 2 $11,792
14 Sep 2026 Cranage & rigging Cranage & rigging — claim 2 $9,604
14 Sep 2026 Electrical subcontract Electrical subcontract — claim 2 $12,917
14 Sep 2026 Controls subcontract Controls subcontract — claim 2 $19,739
14 Sep 2026 Equipment Supply — chiller deposit $83,409
02 Sep 2026 Site labour Site labour — weeks 4–6 $37,486
02 Sep 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 2 $26,714
24 Aug 2026 Pipework & materials Pipework & materials — claim 1 $14,635
24 Aug 2026 Cranage & rigging Cranage & rigging — claim 1 $9,709
24 Aug 2026 Electrical subcontract Electrical subcontract — claim 1 $11,450
24 Aug 2026 Controls subcontract Controls subcontract — claim 1 $16,577
24 Aug 2026 Equipment Progress claim — pumps $89,937
18 Aug 2026 Site labour Site labour — weeks 1–3 $37,549
18 Aug 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 1 $23,617
Emails & activity · 9
↗ RFI 027 — HAC-J2631 — Access to plantroom for crane lift Greg Pollard → Tom Delaney HAC synced 09 Sep 2026 · 12:02
From Greg Pollard <gpollard@harveyind.com.au> · To Tom Delaney <tom@investa.com.au>
Hi Tom, Access to plantroom for crane lift — Saturday OK? Marked-up drawing attached. Greg Pollard
◷ Site coordination meeting — Rhodes Corporate Park Building C Meeting · Tom Delaney · Greg Pollard HAC 07 Sep 2026 · 07:30
Attendees: Tom Delaney, Greg Pollard, Luke Brennan. Commissioning dates agreed with BMS subcontractor.
↙ RFI 024 — HAC-J2631 — Access to plantroom for crane lift Tom Delaney → Greg Pollard HAC synced 26 Aug 2026 · 11:11
From Tom Delaney <tom@investa.com.au> · To Greg Pollard <gpollard@harveyind.com.au>
Hi Greg, Access to plantroom for crane lift — Saturday OK? Please advise by end of week. Tom Delaney
◷ Site coordination meeting — Rhodes Corporate Park Building C Meeting · Tom Delaney · Greg Pollard HAC 24 Aug 2026 · 07:30
Attendees: Tom Delaney, Greg Pollard, Luke Brennan. Commissioning dates agreed with BMS subcontractor.
↗ RFI 021 — HAC-J2631 — Variation: additional FCU to comms room per tenant request Greg Pollard → Tom Delaney HAC synced 12 Aug 2026 · 11:49
From Greg Pollard <gpollard@harveyind.com.au> · To Tom Delaney <tom@investa.com.au>
Hi Tom, Variation: additional FCU to comms room per tenant request Marked-up drawing attached. Greg Pollard
◷ Site coordination meeting — Rhodes Corporate Park Building C Meeting · Tom Delaney · Greg Pollard HAC 10 Aug 2026 · 07:30
Attendees: Tom Delaney, Greg Pollard, Luke Brennan. Plant delivery confirmed for crane lift; road closure permit lodged.
↗ Re: Quotation HAC-Q2651 — Rhodes Corporate Park Building C — base building upgrade Rowan Kennedy → Tom Delaney HAC synced 14 Jul 2026 · 16:38
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Tom Delaney <tom@investa.com.au>
Thanks Tom — appreciated. Greg Pollard will be your project manager and will be in touch this week. Rowan Kennedy
↙ Re: Quotation HAC-Q2651 — Rhodes Corporate Park Building C — base building upgrade Tom Delaney → Rowan Kennedy HAC synced 14 Jul 2026 · 10:00
From Tom Delaney <tom@investa.com.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan, Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule. Tom Delaney
↗ Quotation HAC-Q2651 — Rhodes Corporate Park Building C — base building upgrade Rowan Kennedy → Tom Delaney HAC sent 14 Jun 2026 · 15:46
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Tom Delaney <tom@investa.com.au>
Hi Tom, Please find attached our quotation HAC-Q2651 for Rhodes Corporate Park Building C — base building upgrade — $1,394,000 + GST, valid 30 days. Happy to walk through it. Regards, Rowan Kennedy