iInstallation jobs raised from accepted quotes. Open one to order its fans from FBA, update % complete, raise a progress claim, and hand over to Service at practical completion.
Contract value (incl. variations)
$9,572,700
Earned to date
$4,565,517
Claimed to date
$4,341,032
▼ under-claimed $224,485
Cost to date
$3,745,242
Forecast margin
17.9%
| Contract | Client | Stage | Value | % done | Budget | Cost to date | Forecast cost | Forecast margin | Claimed |
|---|---|---|---|---|---|---|---|---|---|
HAC-J2611 Parramatta Square 6 — Levels 14–16 fitout | Built Pty Ltd | Installation | $1,224,600 | 62% | $1,000,700 | $602,858 | $983,124 | 19.7% | $713,697 |
HAC-J2614 Westmead Institute — Level 3 PC2 laboratories | Westmead Institute for Medical Research | Commissioning | $778,300 | 91% | $639,200 | $592,979 | $650,507 | 16.4% | $665,758 |
HAC-J2618 Penrith Golf Club — gaming & bistro upgrade | Integrated Projects | Installation | $405,500 | 48% | $332,300 | $152,335 | $325,131 | 19.8% | $182,962 |
HAC-J2620 201 Kent St — Level 22 tenancy | Jones Lang LaSalle | Design & Drafting | $268,000 | 4% | $221,600 | $8,274 | $221,010 | 17.5% | $0 |
HAC-J2622 Carlingford Court — food court exhaust & AC | Buildcorp | Procurement | $551,700 | 12% | $450,100 | $52,748 | $448,836 | 18.6% | $62,232 |
HAC-J2623 Lincoln Rise Stage 2 — 64 apartments | EDT Projects | Installation | $848,900 | 66% | $695,700 | $494,926 | $731,464 | 13.8% | $526,658 |
HAC-J2625 Macquarie University Building 12 — chiller replacement | Macquarie University | Procurement | $1,744,700 | 9% | $1,427,100 | $123,805 | $1,422,466 | 18.5% | $147,602 |
HAC-J2627 Burwood RSL — auditorium AHU replacement | Burwood RSL Club | Practical Completion | $312,100 | 100% | $253,000 | $241,553 | $241,553 | 22.6% | $312,100 |
HAC-J2628 Norwest data hall — CRAC units | Shape Australia | Installation | $638,300 | 41% | $532,200 | $216,815 | $530,813 | 16.8% | $246,001 |
HAC-J2630 Seven Hills RSL — kitchen exhaust & make-up air | Seven Hills RSL Club | Commissioning | $217,100 | 88% | $179,200 | $148,876 | $170,380 | 21.5% | $179,585 |
HAC-J2631 Rhodes Corporate Park Building C — base building upgrade | Investa Property Group | Installation | $1,436,000 | 38% | $1,191,000 | $464,904 | $1,203,324 | 16.2% | $512,939 |
HAC-J2633 Fairfield Leisure Centre — pool hall ventilation | Fairfield City Council | Design & Drafting | $356,000 | 2% | $294,700 | $4,258 | $293,064 | 17.7% | $0 |
HAC-J2634 NBN Blacktown exchange — CRAC replacement | Shape Australia | Defects Liability | $458,600 | 100% | $368,600 | $364,332 | $364,332 | 20.6% | $458,600 |
HAC-J2635 Octagon Building L8 — Transport fitout | Formula Interiors | Defects Liability | $332,900 | 100% | $277,800 | $276,579 | $276,579 | 16.9% | $332,900 |