260 assets under maintenance · 9 overdue · 34 FBA fans
Demo 06 Oct 2026
iAgreements set up when an installation is handed over, plus existing service clients. Raise PPM visits puts everything due in the next 14 days onto the Service board.
BarcodeSiteAssetMakeModelSerialLocationFrequencyNext dueStatus
HA-004175 Fox Hills Clubhouse Split system Daikin FTXV 8564015 Room 16 Six-monthly 21 Sep 2026 Overdue Operational
HA-004174 Fox Hills Clubhouse Split system Daikin FTXV 9354210 Level 2 — office 2 Six-monthly 25 Sep 2026 Overdue Operational
HA-004151 Burwood RSL Cooling tower BAC VTL 8756936 Plantroom Monthly 28 Sep 2026 Overdue Operational
HA-004237 Mega Mall Auburn Cooling tower BAC — 9928679 Plantroom #1 Monthly 28 Sep 2026 Overdue Operational
HA-004118 Cabravale Leisure Centre Split system Mitsubishi PKA-M100 9480537 Level 1 — office 18 Six-monthly 29 Sep 2026 Overdue Operational
HA-004302 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 6375041 Ensuite 20 Annual 29 Sep 2026 Overdue Operational
HA-004303 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 2109636 Wing A room 37 Annual 29 Sep 2026 Overdue Operational
HA-004304 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 1308293 Wing A room 36 Annual 29 Sep 2026 Overdue Operational
HA-004117 Cabravale Leisure Centre Split system Mitsubishi PKA-M100 6995827 Room 10 Six-monthly 03 Oct 2026 Overdue Operational
HA-004229 Royal Rehab Ryde Chiller Daikin EWWD-VZ 2650048 Plantroom Monthly 09 Oct 2026 Scheduled Operational
HA-004290 20 Smith St Parramatta AHU Air Change AHU 8417445 Roof #3 Quarterly 09 Oct 2026 Scheduled Operational
HA-004122 Fairfield Council Administration Centre AHU Air Change AHU 9044570 Level 2 plant #2 Quarterly 10 Oct 2026 Scheduled Operational
HA-004143 Fairfield Council Administration Centre Exhaust fan FBA ILC-450 FBA-17-0393 Roof — north #1 Six-monthly 10 Oct 2026 Scheduled Operational
HA-004149 Burwood RSL Chiller Carrier 30XA-302 3171250 Plantroom #1 Monthly 11 Oct 2026 Scheduled Monitor
HA-004152 Burwood RSL AHU Harvey custom AHU 5186661 Plant room 1 Quarterly 11 Oct 2026 Scheduled Operational
HA-004266 Erskine Park Bakery Process exhaust fan FBA MEX-710 FBA-19-0039 Plant deck #4 Quarterly 11 Oct 2026 Scheduled Operational
HA-004287 20 Smith St Parramatta Cooling tower Aquacool — 5693795 Plantroom #2 Monthly 11 Oct 2026 Scheduled Operational
HA-004274 75 Castlereagh St Cooling tower Aquacool — 5228358 Plantroom #2 Monthly 12 Oct 2026 Scheduled Operational
HA-004150 Burwood RSL Chiller Carrier 30XA-302 6099858 Plantroom #2 Monthly 13 Oct 2026 Scheduled Operational
HA-004172 Fox Hills Clubhouse Package unit Temperzone OPA 960 5416976 Plant room 1 Quarterly 13 Oct 2026 Scheduled Operational
HA-004231 Royal Rehab Ryde AHU Air Change AHU 7075425 Roof #2 Quarterly 13 Oct 2026 Scheduled Operational
HA-004294 Parramatta South — Building EA Chiller Daikin EWAD 8025418 Plantroom Monthly 14 Oct 2026 Scheduled Operational
HA-004107 Fairfield Leisure Centre Split system Daikin FTXM60 3598175 Level 2 — office 6 Six-monthly 15 Oct 2026 Scheduled Operational
HA-004111 Cabravale Leisure Centre Package unit Temperzone OPA 590 4288934 Roof #2 Quarterly 15 Oct 2026 Scheduled Operational
HA-004257 Waldorf Pennant Hills Garbage room exhaust FBA ILC-400 FBA-15-0576 Roof Six-monthly 15 Oct 2026 Scheduled Operational
HA-004300 Parramatta South — Building EA Fume cupboard exhaust FBA S1000-SWSI-450-AL FBA-21-0873 Roof #2 Quarterly 15 Oct 2026 Scheduled Operational
HA-004301 Parramatta South — Building EA Fume cupboard exhaust FBA S1000-SWSI-450-AL FBA-23-0311 Carpark B1 Quarterly 16 Oct 2026 Scheduled Operational
HA-004115 Cabravale Leisure Centre Exhaust fan FBA ILC-500 FBA-21-0384 Carpark B1 Six-monthly 19 Oct 2026 Scheduled Operational
HA-004158 Burwood RSL Kitchen exhaust fan FBA S1000-SWSI-630-AL FBA-15-0249 Roof #1 Quarterly 19 Oct 2026 Scheduled Operational
HA-004234 Royal Rehab Ryde Hydrotherapy pool exhaust FBA S1000-SWSI-560-AL FBA-15-0693 Plant deck Quarterly 19 Oct 2026 Scheduled Operational
HA-004269 Erskine Park Bakery Package unit Temperzone OPA 1500 4198517 Roof #3 Quarterly 19 Oct 2026 Scheduled Operational
HA-004345 Bupa Baulkham Hills Hot water plant Rheem commercial 1585740 Roof #2 Six-monthly 19 Oct 2026 Scheduled Operational
HA-004349 Meals Plus & Hope Hostel Thermostatic mixing valve Enware Aquablend 8352011 Ensuite 22 Annual 19 Oct 2026 Scheduled Operational
HA-004169 Burwood RSL Fan coil unit Temperzone FCU 3395856 Level 2 — office 16 Six-monthly 20 Oct 2026 Scheduled Operational
HA-004202 Ettalong Diggers Fan coil unit Daikin FXFQ 8147362 Meeting room 3 Six-monthly 20 Oct 2026 Scheduled Operational
HA-004292 20 Smith St Parramatta AHU Air Change AHU 1540731 Mezzanine #5 Quarterly 20 Oct 2026 Scheduled Operational
HA-004110 Cabravale Leisure Centre Package unit Temperzone OPA 590 8485903 Level 2 plant #1 Quarterly 21 Oct 2026 Scheduled Operational
HA-004210 Marian Nursing Home Split system Mitsubishi MSZ-AP 6572773 Level 2 — office 5 Six-monthly 21 Oct 2026 Scheduled Operational
HA-004220 Marian Nursing Home Split system Mitsubishi MSZ-AP 1450022 Room 20 Six-monthly 21 Oct 2026 Scheduled Operational
HA-004243 Mega Mall Auburn AHU Harvey custom AHU 3244591 Roof #5 Quarterly 21 Oct 2026 Scheduled Operational
HA-004298 Parramatta South — Building EA AHU Air Change AHU 8121489 Plant room 1 Quarterly 21 Oct 2026 Scheduled Operational
HA-004102 Fairfield Leisure Centre AHU Harvey custom AHU 2840511 Roof #2 Quarterly 22 Oct 2026 Scheduled Operational
HA-004322 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 6871476 Room 21 Annual 22 Oct 2026 Scheduled Operational
HA-004230 Royal Rehab Ryde AHU Air Change AHU 4322302 Plant room 1 Quarterly 24 Oct 2026 Scheduled Operational
HA-004296 Parramatta South — Building EA AHU Air Change AHU 1516086 Level 2 plant #2 Quarterly 24 Oct 2026 Scheduled Operational
HA-004101 Fairfield Leisure Centre AHU Harvey custom AHU 4962849 Roof #1 Quarterly 25 Oct 2026 Scheduled Operational
HA-004171 Burwood RSL Fan coil unit Temperzone FCU 9125864 Room 14 Six-monthly 25 Oct 2026 Scheduled Operational
HA-004260 Piccadilly Tower L15–17 Water-cooled packaged unit Temperzone WCP 5969739 Plant room 1 Quarterly 25 Oct 2026 Scheduled Operational
HA-004286 20 Smith St Parramatta Cooling tower Aquacool — 5301831 Plantroom #1 Monthly 25 Oct 2026 Scheduled Operational
HA-004299 Parramatta South — Building EA Fume cupboard exhaust FBA S1000-SWSI-450-AL FBA-17-0446 Roof #1 Quarterly 25 Oct 2026 Scheduled Operational
HA-004273 75 Castlereagh St Cooling tower Aquacool — 2152696 Plantroom #1 Monthly 26 Oct 2026 Scheduled Operational
HA-004124 Fairfield Council Administration Centre AHU Air Change AHU 4363523 Mezzanine #4 Quarterly 27 Oct 2026 Scheduled Operational
HA-004236 Mega Mall Auburn Chiller Carrier 30XW 9370711 Plantroom #2 Monthly 27 Oct 2026 Scheduled Operational
HA-004132 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 9811837 Room 16 Six-monthly 28 Oct 2026 Scheduled Operational
HA-004235 Mega Mall Auburn Chiller Carrier 30XW 3876207 Plantroom #1 Monthly 28 Oct 2026 Scheduled Operational
HA-004289 20 Smith St Parramatta AHU Air Change AHU 3038575 Level 2 plant #2 Quarterly 28 Oct 2026 Scheduled Operational
HA-004103 Fairfield Leisure Centre AHU Harvey custom AHU 8644346 Mezzanine #3 Quarterly 30 Oct 2026 Scheduled Operational
HA-004120 Fairfield Council Administration Centre Chiller Daikin EWAD-TZ 1295105 Plantroom #2 Monthly 30 Oct 2026 Scheduled Operational
HA-004272 75 Castlereagh St Chiller (VSD frictionless) Smardt WC-350 7821966 Plantroom Monthly 31 Oct 2026 Scheduled Operational
HA-004285 20 Smith St Parramatta Chiller (Powerpax) Powerpax centrifugal 1268939 Plantroom Monthly 31 Oct 2026 Scheduled Operational
HA-004100 Fairfield Leisure Centre Chiller Carrier 30RB-262 8569760 Plantroom Monthly 02 Nov 2026 Scheduled Operational
HA-004295 Parramatta South — Building EA AHU Air Change AHU 4078375 Roof #1 Quarterly 02 Nov 2026 Scheduled Operational
HA-004119 Fairfield Council Administration Centre Chiller Daikin EWAD-TZ 9432762 Plantroom #1 Monthly 03 Nov 2026 Scheduled Operational
HA-004187 Ettalong Diggers VRF condenser Daikin VRV IV RXYQ 1788197 Plant room 1 Quarterly 03 Nov 2026 Scheduled Operational
HA-004238 Mega Mall Auburn Cooling tower BAC — 4302982 Plantroom #2 Monthly 03 Nov 2026 Scheduled Operational
HA-004283 75 Castlereagh St AHU Air Change AHU 7054347 Level 2 plant #9 Quarterly 03 Nov 2026 Scheduled Operational
HA-004141 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 6323600 Level 1 — office 17 Six-monthly 04 Nov 2026 Scheduled Operational
HA-004279 75 Castlereagh St AHU Air Change AHU 3768807 Mezzanine #5 Quarterly 04 Nov 2026 Scheduled Operational
HA-004268 Erskine Park Bakery Package unit Temperzone OPA 1500 8786723 Level 2 plant #2 Quarterly 05 Nov 2026 Scheduled Operational
HA-004351 Meals Plus & Hope Hostel Thermostatic mixing valve Enware Aquablend 4252766 Wing B room 6 Annual 05 Nov 2026 Scheduled Operational
HA-004297 Parramatta South — Building EA AHU Air Change AHU 2312602 Level 2 plant #3 Quarterly 06 Nov 2026 Scheduled Operational
HA-004355 Meals Plus & Hope Hostel Backflow prevention device Zurn Wilkins DCV 7677681 Fire service #1 Annual 06 Nov 2026 Scheduled Operational
HA-004180 Fox Hills Clubhouse Kitchen exhaust fan FBA ILC-560 FBA-20-0269 Plant deck Quarterly 07 Nov 2026 Scheduled Operational
HA-004333 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 8798025 Ensuite 14 Annual 09 Nov 2026 Scheduled Operational
HA-004121 Fairfield Council Administration Centre AHU Air Change AHU 9567913 Plant room 1 Quarterly 10 Nov 2026 Scheduled Operational
HA-004221 Marian Nursing Home Split system Mitsubishi MSZ-AP 3105381 Level 1 — office 11 Six-monthly 10 Nov 2026 Scheduled Operational
HA-004330 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 8113343 Wing B room 26 Annual 10 Nov 2026 Scheduled Operational
HA-004123 Fairfield Council Administration Centre AHU Air Change AHU 3642776 Mezzanine #3 Quarterly 11 Nov 2026 Scheduled Operational
HA-004135 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 3381757 Level 2 — office 8 Six-monthly 11 Nov 2026 Scheduled Operational
HA-004136 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 1626241 Room 3 Six-monthly 12 Nov 2026 Scheduled Operational
HA-004342 Bupa Baulkham Hills Backflow prevention device Zurn Wilkins RPZ 3834153 Fire service #3 Annual 12 Nov 2026 Scheduled Operational
HA-004242 Mega Mall Auburn AHU Harvey custom AHU 7470672 Level 2 plant #4 Quarterly 13 Nov 2026 Scheduled Operational
HA-004244 Mega Mall Auburn AHU Harvey custom AHU 3287865 Level 2 plant #6 Quarterly 13 Nov 2026 Scheduled Operational
HA-004259 Piccadilly Tower L15–17 Water-cooled packaged unit Temperzone WCP 6741012 Mezzanine #2 Quarterly 13 Nov 2026 Scheduled Operational
HA-004344 Bupa Baulkham Hills Hot water plant Rheem commercial 8806000 Level 2 plant #1 Six-monthly 13 Nov 2026 Scheduled Operational
HA-004241 Mega Mall Auburn AHU Harvey custom AHU 5636707 Plant room 1 Quarterly 14 Nov 2026 Scheduled Operational
HA-004281 75 Castlereagh St AHU Air Change AHU 7007316 Level 2 plant #7 Quarterly 14 Nov 2026 Scheduled Operational
HA-004214 Marian Nursing Home Split system Mitsubishi MSZ-AP 1498813 Meeting room 8 Six-monthly 16 Nov 2026 Scheduled Operational
HA-004346 Meals Plus & Hope Hostel Thermostatic mixing valve Enware Aquablend 4175736 Wing B room 36 Annual 17 Nov 2026 Scheduled Operational
HA-004262 Piccadilly Tower L15–17 Supplementary DX (comms) Daikin FTXM 8145945 Plant room 1 Quarterly 18 Nov 2026 Scheduled Operational
HA-004277 75 Castlereagh St AHU Air Change AHU 3969870 Level 2 plant #3 Quarterly 18 Nov 2026 Scheduled Operational
HA-004127 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 9651900 Room 13 Six-monthly 19 Nov 2026 Scheduled Operational
HA-004209 Marian Nursing Home Split system Mitsubishi MSZ-AP 4913356 Level 1 — office 13 Six-monthly 19 Nov 2026 Scheduled Operational
HA-004309 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 5682185 Ensuite 36 Annual 19 Nov 2026 Scheduled Operational
HA-004270 Erskine Park Bakery Oven extract fan FBA S1000-SWSI-560-AL FBA-19-0922 Plant room 1 Quarterly 20 Nov 2026 Scheduled Operational
HA-004343 Bupa Baulkham Hills Backflow prevention device Zurn Wilkins RPZ 8499236 Fire service #4 Annual 20 Nov 2026 Scheduled Operational
HA-004114 Cabravale Leisure Centre Exhaust fan FBA ILC-500 FBA-18-0570 Plant deck #2 Six-monthly 21 Nov 2026 Scheduled Operational
HA-004212 Marian Nursing Home Split system Mitsubishi MSZ-AP 3655897 Room 5 Six-monthly 22 Nov 2026 Scheduled Operational
HA-004199 Ettalong Diggers Fan coil unit Daikin FXFQ 4218118 Level 2 — office 18 Six-monthly 23 Nov 2026 Scheduled Operational
HA-004224 Marian Nursing Home Split system Mitsubishi MSZ-AP 9568520 Room 16 Six-monthly 23 Nov 2026 Scheduled Operational
HA-004196 Ettalong Diggers Fan coil unit Daikin FXFQ 7798417 Level 2 — office 6 Six-monthly 24 Nov 2026 Scheduled Operational
HA-004284 75 Castlereagh St AHU Air Change AHU 8242456 Roof #10 Quarterly 24 Nov 2026 Scheduled Operational
HA-004288 20 Smith St Parramatta AHU Air Change AHU 6964881 Mezzanine #1 Quarterly 24 Nov 2026 Scheduled Operational
HA-004139 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 1356463 Level 1 — office 6 Six-monthly 25 Nov 2026 Scheduled Operational
HA-004156 Burwood RSL AHU Harvey custom AHU 6162467 Roof #5 Quarterly 25 Nov 2026 Scheduled Operational
HA-004189 Ettalong Diggers VRF condenser Daikin VRV IV RXYQ 5872483 Mezzanine #3 Quarterly 25 Nov 2026 Scheduled Operational
HA-004190 Ettalong Diggers Fan coil unit Daikin FXFQ 1143739 Level 1 — office 15 Six-monthly 25 Nov 2026 Scheduled Operational
HA-004176 Fox Hills Clubhouse Split system Daikin FTXV 7715813 Level 2 — office 6 Six-monthly 26 Nov 2026 Scheduled Operational
HA-004193 Ettalong Diggers Fan coil unit Daikin FXFQ 5562718 Level 1 — office 14 Six-monthly 26 Nov 2026 Scheduled Operational
HA-004327 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 3115117 Wing A room 40 Annual 26 Nov 2026 Scheduled Operational
HA-004341 Bupa Baulkham Hills Backflow prevention device Zurn Wilkins RPZ 4006870 Kitchen #2 Annual 26 Nov 2026 Scheduled Operational
HA-004206 Marian Nursing Home Split system Mitsubishi MSZ-AP 5008542 Level 2 — office 1 Six-monthly 29 Nov 2026 Scheduled Operational
HA-004218 Marian Nursing Home Split system Mitsubishi MSZ-AP 4414032 Meeting room 6 Six-monthly 29 Nov 2026 Scheduled Operational
HA-004253 Stamford Marque Split system (common) Fujitsu ASTG 3377422 Level 1 — office 11 Six-monthly 29 Nov 2026 Scheduled Operational
HA-004112 Cabravale Leisure Centre Package unit Temperzone OPA 590 3154631 Plant room 1 Quarterly 01 Dec 2026 Scheduled Fault
HA-004358 Northmead Gardens Backflow prevention device Zurn Wilkins RPZ 4377015 Irrigation #2 Annual 01 Dec 2026 Scheduled Operational
HA-004173 Fox Hills Clubhouse Package unit Temperzone OPA 960 7573185 Roof #2 Quarterly 04 Dec 2026 Scheduled Operational
HA-004182 Seven Hills RSL Package unit Temperzone OPA 1200 1967144 Plant room 1 Quarterly 04 Dec 2026 Scheduled Operational
HA-004249 Mega Mall Auburn Carpark exhaust fan FBA S1000-DWDI-900 FBA-23-0818 Roof — north #3 Six-monthly 06 Dec 2026 Scheduled Operational
HA-004227 Marian Nursing Home Split system Mitsubishi MSZ-AP 6140984 Meeting room 15 Six-monthly 07 Dec 2026 Scheduled Operational
HA-004147 Whitlam Library Cabramatta Package unit Temperzone OPA 450 2784640 Mezzanine #2 Quarterly 08 Dec 2026 Scheduled Operational
HA-004226 Marian Nursing Home Split system Mitsubishi MSZ-AP 6486090 Meeting room 16 Six-monthly 08 Dec 2026 Scheduled Operational
HA-004320 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 1773159 Wing B room 18 Annual 08 Dec 2026 Scheduled Operational
HA-004246 Mega Mall Auburn AHU Harvey custom AHU 1975992 Roof #8 Quarterly 09 Dec 2026 Scheduled Operational
HA-004278 75 Castlereagh St AHU Air Change AHU 6489079 Mezzanine #4 Quarterly 09 Dec 2026 Scheduled Operational
HA-004280 75 Castlereagh St AHU Air Change AHU 3985719 Roof #6 Quarterly 09 Dec 2026 Scheduled Operational
HA-004184 Seven Hills RSL Package unit Temperzone OPA 1200 3797574 Plant room 1 Quarterly 10 Dec 2026 Scheduled Operational
HA-004335 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 9429909 Wing A room 13 Annual 10 Dec 2026 Scheduled Operational
HA-004161 Burwood RSL Fan coil unit Temperzone FCU 3521584 Room 3 Six-monthly 11 Dec 2026 Scheduled Operational
HA-004159 Burwood RSL Kitchen exhaust fan FBA S1000-SWSI-630-AL FBA-21-0712 Roof #2 Quarterly 12 Dec 2026 Scheduled Operational
HA-004155 Burwood RSL AHU Harvey custom AHU 9130875 Plant room 1 Quarterly 13 Dec 2026 Scheduled Operational
HA-004201 Ettalong Diggers Fan coil unit Daikin FXFQ 1700348 Level 1 — office 9 Six-monthly 14 Dec 2026 Scheduled Operational
HA-004261 Piccadilly Tower L15–17 Supplementary DX (comms) Daikin FTXM 3271702 Mezzanine #1 Quarterly 14 Dec 2026 Scheduled Operational
HA-004276 75 Castlereagh St AHU Air Change AHU 3091179 Mezzanine #2 Quarterly 14 Dec 2026 Scheduled Operational
HA-004258 Piccadilly Tower L15–17 Water-cooled packaged unit Temperzone WCP 2788325 Mezzanine #1 Quarterly 15 Dec 2026 Scheduled Operational
HA-004264 Erskine Park Bakery Process exhaust fan FBA MEX-710 FBA-19-0693 Plant deck #2 Quarterly 15 Dec 2026 Scheduled Operational
HA-004263 Erskine Park Bakery Process exhaust fan FBA MEX-710 FBA-22-0227 Roof — north #1 Quarterly 18 Dec 2026 Scheduled Operational
HA-004109 Fairfield Leisure Centre Split system Daikin FTXM60 1801195 Meeting room 18 Six-monthly 19 Dec 2026 Scheduled Operational
HA-004154 Burwood RSL AHU Harvey custom AHU 7866419 Mezzanine #3 Quarterly 19 Dec 2026 Scheduled Operational
HA-004181 Seven Hills RSL Package unit Temperzone OPA 1200 7087296 Roof #1 Quarterly 19 Dec 2026 Scheduled Operational
HA-004228 Marian Nursing Home Package unit Temperzone OPA 350 4835140 Roof Quarterly 19 Dec 2026 Scheduled Operational
HA-004240 Mega Mall Auburn AHU Harvey custom AHU 4153439 Roof #2 Quarterly 21 Dec 2026 Scheduled Operational
HA-004140 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 3511202 Meeting room 7 Six-monthly 23 Dec 2026 Scheduled Operational
HA-004185 Seven Hills RSL Kitchen exhaust fan FBA ILC-630 FBA-17-0928 Carpark B1 Quarterly 23 Dec 2026 Scheduled Operational
HA-004265 Erskine Park Bakery Process exhaust fan FBA MEX-710 FBA-24-0700 Roof #3 Quarterly 24 Dec 2026 Scheduled Operational
HA-004157 Burwood RSL AHU Harvey custom AHU 8990063 Mezzanine #6 Quarterly 25 Dec 2026 Scheduled Operational
HA-004275 75 Castlereagh St AHU Air Change AHU 4589241 Roof #1 Quarterly 25 Dec 2026 Scheduled Operational
HA-004183 Seven Hills RSL Package unit Temperzone OPA 1200 1403645 Roof #3 Quarterly 26 Dec 2026 Scheduled Operational
HA-004188 Ettalong Diggers VRF condenser Daikin VRV IV RXYQ 1813786 Mezzanine #2 Quarterly 26 Dec 2026 Scheduled Operational
HA-004168 Burwood RSL Fan coil unit Temperzone FCU 4695907 Meeting room 4 Six-monthly 27 Dec 2026 Scheduled Operational
HA-004267 Erskine Park Bakery Package unit Temperzone OPA 1500 4256203 Roof #1 Quarterly 27 Dec 2026 Scheduled Operational
HA-004291 20 Smith St Parramatta AHU Air Change AHU 4702490 Mezzanine #4 Quarterly 27 Dec 2026 Scheduled Operational
HA-004233 Royal Rehab Ryde AHU Air Change AHU 2730075 Mezzanine #4 Quarterly 28 Dec 2026 Scheduled Operational
HA-004271 Erskine Park Bakery Oven extract fan FBA S1000-SWSI-560-AL FBA-21-0058 Roof #2 Quarterly 28 Dec 2026 Scheduled Operational
HA-004282 75 Castlereagh St AHU Air Change AHU 4882667 Mezzanine #8 Quarterly 28 Dec 2026 Scheduled Operational
HA-004186 Seven Hills RSL Kitchen exhaust fan FBA ILC-630 FBA-17-0248 Plant deck #2 Quarterly 29 Dec 2026 Scheduled Operational
HA-004245 Mega Mall Auburn AHU Harvey custom AHU 1899143 Roof #7 Quarterly 29 Dec 2026 Scheduled Operational
HA-004208 Marian Nursing Home Split system Mitsubishi MSZ-AP 4353131 Level 1 — office 5 Six-monthly 30 Dec 2026 Scheduled Operational
HA-004126 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 2799358 Level 1 — office 17 Six-monthly 31 Dec 2026 Scheduled Operational
HA-004153 Burwood RSL AHU Harvey custom AHU 1125776 Level 2 plant #2 Quarterly 31 Dec 2026 Scheduled Operational
HA-004225 Marian Nursing Home Split system Mitsubishi MSZ-AP 5256132 Room 12 Six-monthly 31 Dec 2026 Scheduled Operational
HA-004252 Stamford Marque Carpark exhaust fan FBA S1000-SWSI-710-AL FBA-16-0833 Carpark B1 Six-monthly 31 Dec 2026 Scheduled Operational
HA-004128 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 6275324 Level 2 — office 15 Six-monthly 01 Jan 2027 Scheduled Operational
HA-004146 Whitlam Library Cabramatta Package unit Temperzone OPA 450 5149944 Mezzanine #1 Quarterly 01 Jan 2027 Scheduled Operational
HA-004177 Fox Hills Clubhouse Split system Daikin FTXV 7043377 Meeting room 19 Six-monthly 01 Jan 2027 Scheduled Operational
HA-004293 20 Smith St Parramatta AHU Air Change AHU 8889842 Level 2 plant #6 Quarterly 01 Jan 2027 Scheduled Operational
HA-004232 Royal Rehab Ryde AHU Air Change AHU 6513145 Roof #3 Quarterly 03 Jan 2027 Scheduled Operational
HA-004239 Mega Mall Auburn AHU Harvey custom AHU 1613215 Level 2 plant #1 Quarterly 03 Jan 2027 Scheduled Operational
HA-004129 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 9875273 Meeting room 8 Six-monthly 05 Jan 2027 Scheduled Operational
HA-004248 Mega Mall Auburn Carpark exhaust fan FBA S1000-DWDI-900 FBA-22-0327 Roof — north #2 Six-monthly 05 Jan 2027 Scheduled Operational
HA-004160 Burwood RSL Fan coil unit Temperzone FCU 2612631 Level 1 — office 7 Six-monthly 08 Jan 2027 Scheduled Operational
HA-004254 Stamford Marque Split system (common) Fujitsu ASTG 2166073 Room 7 Six-monthly 08 Jan 2027 Scheduled Operational
HA-004312 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 6531448 Wing A room 12 Annual 11 Jan 2027 Scheduled Operational
HA-004329 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 6540751 Room 16 Annual 12 Jan 2027 Scheduled Operational
HA-004130 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 7021320 Room 10 Six-monthly 13 Jan 2027 Scheduled Operational
HA-004148 Whitlam Library Cabramatta Exhaust fan FBA ILC-400 FBA-25-0434 Roof Six-monthly 15 Jan 2027 Scheduled Operational
HA-004223 Marian Nursing Home Split system Mitsubishi MSZ-AP 9625784 Room 13 Six-monthly 15 Jan 2027 Scheduled Operational
HA-004105 Fairfield Leisure Centre Pool hall exhaust fan FBA S1000-SWSI-800-AL FBA-19-0492 Roof — north #2 Six-monthly 17 Jan 2027 Scheduled Operational
HA-004142 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 1383676 Room 2 Six-monthly 17 Jan 2027 Scheduled Operational
HA-004347 Meals Plus & Hope Hostel Thermostatic mixing valve Enware Aquablend 5457122 Wing B room 35 Annual 21 Jan 2027 Scheduled Operational
HA-004113 Cabravale Leisure Centre Exhaust fan FBA ILC-500 FBA-23-0197 Plant deck #1 Six-monthly 22 Jan 2027 Scheduled Operational
HA-004106 Fairfield Leisure Centre Split system Daikin FTXM60 8984705 Level 2 — office 11 Six-monthly 27 Jan 2027 Scheduled Operational
HA-004166 Burwood RSL Fan coil unit Temperzone FCU 2668772 Room 8 Six-monthly 28 Jan 2027 Scheduled Operational
HA-004162 Burwood RSL Fan coil unit Temperzone FCU 9100273 Meeting room 16 Six-monthly 31 Jan 2027 Scheduled Operational
HA-004255 Stamford Marque Split system (common) Fujitsu ASTG 6547336 Meeting room 7 Six-monthly 02 Feb 2027 Scheduled Operational
HA-004354 Meals Plus & Hope Hostel Thermostatic mixing valve Enware Aquablend 6771368 Room 25 Annual 02 Feb 2027 Scheduled Operational
HA-004250 Mega Mall Auburn Carpark exhaust fan FBA S1000-DWDI-900 FBA-15-0345 Carpark B1 Six-monthly 03 Feb 2027 Scheduled Operational
HA-004356 Meals Plus & Hope Hostel Backflow prevention device Zurn Wilkins DCV 7582616 Irrigation #2 Annual 03 Feb 2027 Scheduled Operational
HA-004191 Ettalong Diggers Fan coil unit Daikin FXFQ 5514840 Meeting room 10 Six-monthly 04 Feb 2027 Scheduled Operational
HA-004359 Northmead Gardens Sewer pump station Grundfos SEG 8386636 Mezzanine Six-monthly 07 Feb 2027 Scheduled Operational
HA-004211 Marian Nursing Home Split system Mitsubishi MSZ-AP 5634651 Level 2 — office 13 Six-monthly 09 Feb 2027 Scheduled Operational
HA-004222 Marian Nursing Home Split system Mitsubishi MSZ-AP 3841074 Meeting room 18 Six-monthly 09 Feb 2027 Scheduled Operational
HA-004308 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 4008599 Ensuite 35 Annual 09 Feb 2027 Scheduled Operational
HA-004195 Ettalong Diggers Fan coil unit Daikin FXFQ 7405777 Level 1 — office 11 Six-monthly 10 Feb 2027 Scheduled Operational
HA-004215 Marian Nursing Home Split system Mitsubishi MSZ-AP 9793188 Level 1 — office 3 Six-monthly 11 Feb 2027 Scheduled Operational
HA-004198 Ettalong Diggers Fan coil unit Daikin FXFQ 5805594 Meeting room 20 Six-monthly 16 Feb 2027 Scheduled Operational
HA-004163 Burwood RSL Fan coil unit Temperzone FCU 1785631 Meeting room 15 Six-monthly 18 Feb 2027 Scheduled Operational
HA-004192 Ettalong Diggers Fan coil unit Daikin FXFQ 4133222 Room 2 Six-monthly 20 Feb 2027 Scheduled Operational
HA-004194 Ettalong Diggers Fan coil unit Daikin FXFQ 5054448 Room 7 Six-monthly 21 Feb 2027 Scheduled Operational
HA-004205 Ettalong Diggers Exhaust fan FBA ILC-450 FBA-22-0121 Roof #2 Six-monthly 22 Feb 2027 Scheduled Operational
HA-004336 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 3252360 Room 21 Annual 22 Feb 2027 Scheduled Operational
HA-004145 Fairfield Council Administration Centre Exhaust fan FBA ILC-450 FBA-23-0797 Carpark B1 Six-monthly 24 Feb 2027 Scheduled Operational
HA-004170 Burwood RSL Fan coil unit Temperzone FCU 8930870 Room 12 Six-monthly 24 Feb 2027 Scheduled Operational
HA-004200 Ettalong Diggers Fan coil unit Daikin FXFQ 6393956 Level 1 — office 3 Six-monthly 24 Feb 2027 Scheduled Operational
HA-004310 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 3993498 Ensuite 36 Annual 24 Feb 2027 Scheduled Operational
HA-004203 Ettalong Diggers Fan coil unit Daikin FXFQ 2723151 Room 12 Six-monthly 25 Feb 2027 Scheduled Operational
HA-004138 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 6107082 Level 2 — office 16 Six-monthly 26 Feb 2027 Scheduled Operational
HA-004219 Marian Nursing Home Split system Mitsubishi MSZ-AP 1385569 Meeting room 5 Six-monthly 03 Mar 2027 Scheduled Operational
HA-004256 Waldorf Pennant Hills Carpark exhaust fan FBA S1000-SWSI-630-AL FBA-20-0109 Carpark B1 Six-monthly 03 Mar 2027 Scheduled Operational
HA-004133 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 7372336 Meeting room 7 Six-monthly 05 Mar 2027 Scheduled Operational
HA-004247 Mega Mall Auburn Carpark exhaust fan FBA S1000-DWDI-900 FBA-22-0507 Plant deck #1 Six-monthly 05 Mar 2027 Scheduled Operational
HA-004321 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 5229065 Wing A room 48 Annual 06 Mar 2027 Scheduled Operational
HA-004108 Fairfield Leisure Centre Split system Daikin FTXM60 1949695 Meeting room 18 Six-monthly 09 Mar 2027 Scheduled Operational
HA-004164 Burwood RSL Fan coil unit Temperzone FCU 5819158 Level 2 — office 12 Six-monthly 09 Mar 2027 Scheduled Operational
HA-004204 Ettalong Diggers Exhaust fan FBA ILC-450 FBA-15-0262 Plant deck #1 Six-monthly 10 Mar 2027 Scheduled Operational
HA-004207 Marian Nursing Home Split system Mitsubishi MSZ-AP 9260601 Level 1 — office 4 Six-monthly 11 Mar 2027 Scheduled Operational
HA-004178 Fox Hills Clubhouse Split system Daikin FTXV 3290462 Level 1 — office 15 Six-monthly 14 Mar 2027 Scheduled Operational
HA-004179 Fox Hills Clubhouse Split system Daikin FTXV 6221319 Level 1 — office 2 Six-monthly 14 Mar 2027 Scheduled Operational
HA-004104 Fairfield Leisure Centre Pool hall exhaust fan FBA S1000-SWSI-800-AL FBA-20-0317 Roof — north #1 Six-monthly 17 Mar 2027 Scheduled Operational
HA-004339 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 8156827 Room 21 Annual 17 Mar 2027 Scheduled Operational
HA-004348 Meals Plus & Hope Hostel Thermostatic mixing valve Enware Aquablend 3125132 Ensuite 30 Annual 17 Mar 2027 Scheduled Operational
HA-004137 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 6966001 Level 1 — office 12 Six-monthly 18 Mar 2027 Scheduled Operational
HA-004318 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 6395699 Room 7 Annual 18 Mar 2027 Scheduled Operational
HA-004217 Marian Nursing Home Split system Mitsubishi MSZ-AP 7596135 Level 2 — office 19 Six-monthly 19 Mar 2027 Scheduled Operational
HA-004165 Burwood RSL Fan coil unit Temperzone FCU 9769511 Level 1 — office 7 Six-monthly 20 Mar 2027 Scheduled Operational
HA-004216 Marian Nursing Home Split system Mitsubishi MSZ-AP 6977380 Level 1 — office 17 Six-monthly 22 Mar 2027 Scheduled Operational
HA-004319 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 1170569 Wing A room 43 Annual 22 Mar 2027 Scheduled Operational
HA-004144 Fairfield Council Administration Centre Exhaust fan FBA ILC-450 FBA-18-0710 Roof #2 Six-monthly 23 Mar 2027 Scheduled Operational
HA-004305 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 8935380 Ensuite 20 Annual 23 Mar 2027 Scheduled Operational
HA-004134 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 3228475 Level 2 — office 4 Six-monthly 25 Mar 2027 Scheduled Operational
HA-004251 Stamford Marque Carpark exhaust fan FBA S1000-SWSI-710-AL FBA-20-0480 Roof #1 Six-monthly 25 Mar 2027 Scheduled Operational
HA-004125 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 2347116 Level 2 — office 9 Six-monthly 26 Mar 2027 Scheduled Operational
HA-004213 Marian Nursing Home Split system Mitsubishi MSZ-AP 5193330 Meeting room 9 Six-monthly 28 Mar 2027 Scheduled Operational
HA-004197 Ettalong Diggers Fan coil unit Daikin FXFQ 2104694 Meeting room 11 Six-monthly 31 Mar 2027 Scheduled Operational
HA-004131 Fairfield Council Administration Centre Fan coil unit Temperzone FCU 2874781 Meeting room 15 Six-monthly 01 Apr 2027 Scheduled Operational
HA-004167 Burwood RSL Fan coil unit Temperzone FCU 5020237 Meeting room 1 Six-monthly 01 Apr 2027 Scheduled Operational
HA-004116 Cabravale Leisure Centre Split system Mitsubishi PKA-M100 3270182 Room 6 Six-monthly 04 Apr 2027 Scheduled Operational
HA-004353 Meals Plus & Hope Hostel Thermostatic mixing valve Enware Aquablend 5820068 Wing A room 1 Annual 07 Apr 2027 Scheduled Operational
HA-004334 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 8053073 Ensuite 40 Annual 13 May 2027 Scheduled Operational
HA-004307 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 8428901 Wing B room 4 Annual 15 May 2027 Scheduled Operational
HA-004306 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 1805508 Ensuite 22 Annual 28 May 2027 Scheduled Operational
HA-004357 Northmead Gardens Backflow prevention device Zurn Wilkins RPZ 7409716 Irrigation #1 Annual 28 May 2027 Scheduled Operational
HA-004323 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 8599981 Ensuite 23 Annual 05 Jun 2027 Scheduled Operational
HA-004316 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 2388464 Ensuite 16 Annual 19 Jun 2027 Scheduled Operational
HA-004317 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 9606635 Room 28 Annual 19 Jun 2027 Scheduled Operational
HA-004328 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 2919733 Wing B room 10 Annual 19 Jun 2027 Scheduled Operational
HA-004337 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 5401352 Ensuite 14 Annual 23 Jun 2027 Scheduled Operational
HA-004324 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 4376309 Wing A room 17 Annual 13 Jul 2027 Scheduled Operational
HA-004311 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 2364805 Wing A room 22 Annual 22 Jul 2027 Scheduled Operational
HA-004352 Meals Plus & Hope Hostel Thermostatic mixing valve Enware Aquablend 6155404 Ensuite 21 Annual 07 Aug 2027 Scheduled Operational
HA-004326 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 6925719 Wing A room 7 Annual 08 Aug 2027 Scheduled Operational
HA-004340 Bupa Baulkham Hills Backflow prevention device Zurn Wilkins RPZ 7410045 Irrigation #1 Annual 08 Aug 2027 Scheduled Operational
HA-004331 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 1479334 Ensuite 11 Annual 10 Aug 2027 Scheduled Operational
HA-004315 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 2492878 Room 11 Annual 21 Aug 2027 Scheduled Operational
HA-004325 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 6119019 Wing B room 15 Annual 27 Aug 2027 Scheduled Operational
HA-004332 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 6664063 Ensuite 35 Annual 31 Aug 2027 Scheduled Operational
HA-004338 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 9242764 Wing A room 44 Annual 04 Sep 2027 Scheduled Operational
HA-004313 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 7327709 Wing B room 22 Annual 12 Sep 2027 Scheduled Operational
HA-004350 Meals Plus & Hope Hostel Thermostatic mixing valve Enware Aquablend 8668603 Wing A room 42 Annual 16 Sep 2027 Scheduled Operational
HA-004314 Bupa Baulkham Hills Thermostatic mixing valve Enware Aquablend 3661138 Wing B room 11 Annual 04 Oct 2027 Scheduled Operational