Harvey

HAC-J2622

Carlingford Court — food court exhaust & AC · Buildcorp
Demo 06 Oct 2026
← Contracts
1
Enquiry
direct order
✓
Quote
3
Jobin progress
✓
Invoices
5
Look after it
not yet
Next step
Update % complete as work progresses
Currently 12% and fully claimed. Move the card on the Contracts board when the stage changes.
ContractProcurementOn track
Client
Buildcorp · Adam Lazzaro
Site
Pennant Hills Rd, Carlingford
Project manager
Matt Corrigan
Program
24 Sep 2026 → PC 28 Dec 2026
Scope
Rooftop packaged units, kitchen exhaust risers, make-up air.
From quote
HAC-Q2645
12% complete
MoneyForecast margin 18.6%
Contract value$534,000.00 Approved variations$17,700.00 Revised contract$551,700.00 Cost budget (from estimate)$450,100.00 Cost to date$52,748.00 Committed — FBA fans in build$15,681.00 Committed — open POs$97,350.00 Forecast final cost$448,836.00 Earned (12%)$66,204.00 Claimed to date$62,231.76 Retention held by client$3,111.59
Equipment $18,609 Ductwork (Parramatta shop) $8,723 Site labour $12,671 Controls subcontract $4,062 Electrical subcontract $3,259 Cranage & rigging $2,187 Pipework & materials $3,237
Equipment schedule2 FBA fan line(s) · 0 not yet ordered · 2 in the factory
TagTypeMake / modelLocationkWSupplyFBA works orderSerial
PAC-01..03 (×3) Rooftop packaged unit OPA 1000 Roof 22 Supplier — —
KEF-FC1 Kitchen exhaust fan Series 1000 SWSI 630 aerofoil Roof 5.5 FBA WO-26119 · Fabrication —
MUA-FC1 Make-up air fan Series 1000 DWDI 560 aerofoil Roof 4 FBA WO-26120 · Released —
Costs to date$52,748
DateCategoryDescriptionAmount
06 Oct 2026 Pipework & materials Pipework & materials — claim 2 $1,589
06 Oct 2026 Pipework & materials Pipework & materials — claim 1 $1,648
06 Oct 2026 Cranage & rigging Cranage & rigging — claim 2 $1,138
06 Oct 2026 Cranage & rigging Cranage & rigging — claim 1 $1,049
06 Oct 2026 Electrical subcontract Electrical subcontract — claim 2 $1,480
06 Oct 2026 Electrical subcontract Electrical subcontract — claim 1 $1,779
06 Oct 2026 Controls subcontract Controls subcontract — claim 2 $1,848
06 Oct 2026 Controls subcontract Controls subcontract — claim 1 $2,214
06 Oct 2026 Site labour Site labour — weeks 7–9 $4,197
06 Oct 2026 Site labour Site labour — weeks 4–6 $4,202
06 Oct 2026 Site labour Site labour — weeks 1–3 $4,272
06 Oct 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 3 $2,941
06 Oct 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 2 $3,040
06 Oct 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 1 $2,742
06 Oct 2026 Equipment Delivery — chiller deposit $10,570
06 Oct 2026 Equipment Progress claim — pumps $8,039
Emails & activity · 5
↗ RFI 015 — HAC-J2622 — Confirm chilled beam supply temperature for L15 tenancy Matt Corrigan → Adam Lazzaro HAC synced 03 Oct 2026 · 12:36
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Adam Lazzaro <adam@buildcorp.com.au>
Hi Adam, Confirm chilled beam supply temperature for L15 tenancy Marked-up drawing attached. Matt Corrigan
◷ Site coordination meeting — Carlingford Court Meeting · Adam Lazzaro · Matt Corrigan HAC 01 Oct 2026 · 07:30
Attendees: Adam Lazzaro, Matt Corrigan, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↗ Re: Quotation HAC-Q2645 — Carlingford Court — food court exhaust & AC Rowan Kennedy → Adam Lazzaro HAC synced 27 Aug 2026 · 16:03
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Adam Lazzaro <adam@buildcorp.com.au>
Thanks Adam — appreciated. Greg Pollard will be your project manager and will be in touch this week. Rowan Kennedy
↙ Re: Quotation HAC-Q2645 — Carlingford Court — food court exhaust & AC Adam Lazzaro → Rowan Kennedy HAC synced 27 Aug 2026 · 10:00
From Adam Lazzaro <adam@buildcorp.com.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan, Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule. Adam Lazzaro
↗ Quotation HAC-Q2645 — Carlingford Court — food court exhaust & AC Rowan Kennedy → Adam Lazzaro HAC sent 25 Jul 2026 · 14:17
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Adam Lazzaro <adam@buildcorp.com.au>
Hi Adam, Please find attached our quotation HAC-Q2645 for Carlingford Court — food court exhaust & AC — $534,000 + GST, valid 30 days. Happy to walk through it. Regards, Rowan Kennedy