Harvey

HAC-J2618

Penrith Golf Club — gaming & bistro upgrade · Integrated Projects
Demo 06 Oct 2026
← Contracts
✓
Quote accepted
HAC-Q2643
✓
Contract
Installation
✓
FBA fans
1/1 delivered
4
Practical completion
19 Nov 2026
5
Service handover
pending
ContractInstallationOn track
Client
Integrated Projects · Warren Lowe
Site
Mulgoa Rd, Penrith
Project manager
Matt Corrigan
Program
10 Aug 2026 → PC 19 Nov 2026
Scope
FCUs + condensers to gaming room and bistro, kitchen exhaust, evaporative cooler to kitchen.
From quote
HAC-Q2643
48% complete
MoneyForecast margin 19.8%
Contract value$386,500.00 Approved variations$19,000.00 Revised contract$405,500.00 Cost budget (from estimate)$332,300.00 Cost to date$152,335.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$325,131.00 Earned (48%)$194,640.00 Claimed to date$182,961.60 Retention held by client$9,148.08
Equipment $51,777 FBA fans (inter-company) $5,517 Ductwork (Parramatta shop) $24,126 Site labour $36,693 Controls subcontract $11,090 Electrical subcontract $9,107 Cranage & rigging $5,875 Pipework & materials $8,150
Equipment schedule1 FBA fan line(s) · 0 not yet ordered
TagTypeMake / modelLocationkWSupplyFBA works orderSerial
CU-01..04 (×4) Condensing unit PUHZ-ZRP250 Roof 7.2 Supplier — —
KEF-01 Kitchen exhaust fan In-line Centrifugal 560 backward inclined Roof 3 FBA WO-26118 · Dispatched FBA-26-0410
Costs to date$152,335
DateCategoryDescriptionAmount
28 Sep 2026 FBA fans (inter-company) WO-26118 In-line Centrifugal 560 backward inclined — KEF-01 Kitchen exhaust fan $5,517
24 Sep 2026 Site labour Site labour — weeks 7–9 $12,300
24 Sep 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 3 $8,903
21 Sep 2026 Pipework & materials Pipework & materials — claim 2 $4,020
21 Sep 2026 Cranage & rigging Cranage & rigging — claim 2 $2,649
21 Sep 2026 Electrical subcontract Electrical subcontract — claim 2 $4,384
21 Sep 2026 Controls subcontract Controls subcontract — claim 2 $5,879
21 Sep 2026 Equipment Supply — VSDs $27,724
09 Sep 2026 Site labour Site labour — weeks 4–6 $13,469
09 Sep 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 2 $7,024
31 Aug 2026 Pipework & materials Pipework & materials — claim 1 $4,130
31 Aug 2026 Cranage & rigging Cranage & rigging — claim 1 $3,226
31 Aug 2026 Electrical subcontract Electrical subcontract — claim 1 $4,723
31 Aug 2026 Controls subcontract Controls subcontract — claim 1 $5,211
31 Aug 2026 Equipment Supply — chiller deposit $24,053
25 Aug 2026 Site labour Site labour — weeks 1–3 $10,924
25 Aug 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 1 $8,199
Emails & activity · 9
↗ RFI 019 — HAC-J2618 — Access to plantroom for crane lift Matt Corrigan → Warren Lowe HAC synced 16 Sep 2026 · 10:10
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Warren Lowe <warren@integratedprojects.com.au>
Hi Warren, Access to plantroom for crane lift — Saturday OK? Marked-up drawing attached. Matt Corrigan
◷ Site coordination meeting — Penrith Golf Club Meeting · Warren Lowe · Matt Corrigan HAC 14 Sep 2026 · 07:30
Attendees: Warren Lowe, Matt Corrigan, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↙ RFI 016 — HAC-J2618 — BMS points list Warren Lowe → Matt Corrigan HAC synced 02 Sep 2026 · 15:43
From Warren Lowe <warren@integratedprojects.com.au> · To Matt Corrigan <mcorrigan@harveyind.com.au>
Hi Matt, BMS points list — confirm naming convention Please advise by end of week. Warren Lowe
◷ Site coordination meeting — Penrith Golf Club Meeting · Warren Lowe · Matt Corrigan HAC 31 Aug 2026 · 07:30
Attendees: Warren Lowe, Matt Corrigan, Luke Brennan. Plant delivery confirmed for crane lift; road closure permit lodged.
↗ RFI 013 — HAC-J2618 — Fire mode testing date with certifier Matt Corrigan → Warren Lowe HAC synced 19 Aug 2026 · 13:30
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Warren Lowe <warren@integratedprojects.com.au>
Hi Warren, Fire mode testing date with certifier Marked-up drawing attached. Matt Corrigan
◷ Site coordination meeting — Penrith Golf Club Meeting · Warren Lowe · Matt Corrigan HAC 17 Aug 2026 · 07:30
Attendees: Warren Lowe, Matt Corrigan, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↗ Re: Quotation HAC-Q2643 — Penrith Golf Club — gaming & bistro upgrade Rowan Kennedy → Warren Lowe HAC synced 18 Jul 2026 · 16:25
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Warren Lowe <warren@integratedprojects.com.au>
Thanks Warren — appreciated. Greg Pollard will be your project manager and will be in touch this week. Rowan Kennedy
↙ Re: Quotation HAC-Q2643 — Penrith Golf Club — gaming & bistro upgrade Warren Lowe → Rowan Kennedy HAC synced 18 Jul 2026 · 10:00
From Warren Lowe <warren@integratedprojects.com.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan, Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule. Warren Lowe
↗ Quotation HAC-Q2643 — Penrith Golf Club — gaming & bistro upgrade Rowan Kennedy → Warren Lowe HAC sent 23 Jun 2026 · 14:07
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Warren Lowe <warren@integratedprojects.com.au>
Hi Warren, Please find attached our quotation HAC-Q2643 for Penrith Golf Club — gaming & bistro upgrade — $386,500 + GST, valid 30 days. Happy to walk through it. Regards, Rowan Kennedy