Quote accepted
HAC-Q2643
✓
Contract
Installation
✓
FBA fans
1/1 delivered
4
Practical completion
19 Nov 2026
5
Service handover
pending
ContractInstallationOn track
- Client
- Integrated Projects · Warren Lowe
- Site
- Mulgoa Rd, Penrith
- Project manager
- Matt Corrigan
- Program
- 10 Aug 2026 → PC 19 Nov 2026
- Scope
- FCUs + condensers to gaming room and bistro, kitchen exhaust, evaporative cooler to kitchen.
- From quote
- HAC-Q2643
48% complete
MoneyForecast margin 19.8%
Contract value$386,500.00 Approved variations$19,000.00 Revised contract$405,500.00 Cost budget (from estimate)$332,300.00 Cost to date$152,335.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$325,131.00 Earned (48%)$194,640.00 Claimed to date$182,961.60 Retention held by client$9,148.08
Equipment $51,777 FBA fans (inter-company) $5,517 Ductwork (Parramatta shop) $24,126 Site labour $36,693 Controls subcontract $11,090 Electrical subcontract $9,107 Cranage & rigging $5,875 Pipework & materials $8,150
Equipment schedule1 FBA fan line(s) · 0 not yet ordered
| Tag | Type | Make / model | Location | kW | Supply | FBA works order | Serial | |
|---|---|---|---|---|---|---|---|---|
| CU-01..04 (×4) | Condensing unit | PUHZ-ZRP250 | Roof | 7.2 | Supplier | — | — | |
| KEF-01 | Kitchen exhaust fan | In-line Centrifugal 560 backward inclined | Roof | 3 | FBA | WO-26118 · Dispatched | FBA-26-0410 | |
Costs to date$152,335
| Date | Category | Description | Amount | |
|---|---|---|---|---|
| 28 Sep 2026 | FBA fans (inter-company) | WO-26118 In-line Centrifugal 560 backward inclined — KEF-01 Kitchen exhaust fan | $5,517 | |
| 24 Sep 2026 | Site labour | Site labour — weeks 7–9 | $12,300 | |
| 24 Sep 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 3 | $8,903 | |
| 21 Sep 2026 | Pipework & materials | Pipework & materials — claim 2 | $4,020 | |
| 21 Sep 2026 | Cranage & rigging | Cranage & rigging — claim 2 | $2,649 | |
| 21 Sep 2026 | Electrical subcontract | Electrical subcontract — claim 2 | $4,384 | |
| 21 Sep 2026 | Controls subcontract | Controls subcontract — claim 2 | $5,879 | |
| 21 Sep 2026 | Equipment | Supply — VSDs | $27,724 | |
| 09 Sep 2026 | Site labour | Site labour — weeks 4–6 | $13,469 | |
| 09 Sep 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 2 | $7,024 | |
| 31 Aug 2026 | Pipework & materials | Pipework & materials — claim 1 | $4,130 | |
| 31 Aug 2026 | Cranage & rigging | Cranage & rigging — claim 1 | $3,226 | |
| 31 Aug 2026 | Electrical subcontract | Electrical subcontract — claim 1 | $4,723 | |
| 31 Aug 2026 | Controls subcontract | Controls subcontract — claim 1 | $5,211 | |
| 31 Aug 2026 | Equipment | Supply — chiller deposit | $24,053 | |
| 25 Aug 2026 | Site labour | Site labour — weeks 1–3 | $10,924 | |
| 25 Aug 2026 | Ductwork (Parramatta shop) | Ductwork (Parramatta shop) — claim 1 | $8,199 | |
Emails & activity · 9
↗ RFI 019 — HAC-J2618 — Access to plantroom for crane lift HAC synced 16 Sep 2026 · 10:10
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Warren Lowe <warren@integratedprojects.com.au>
Hi Warren,
Access to plantroom for crane lift — Saturday OK?
Marked-up drawing attached.
Matt Corrigan◷ Site coordination meeting — Penrith Golf Club HAC 14 Sep 2026 · 07:30
Attendees: Warren Lowe, Matt Corrigan, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↙ RFI 016 — HAC-J2618 — BMS points list HAC synced 02 Sep 2026 · 15:43
From Warren Lowe <warren@integratedprojects.com.au> · To Matt Corrigan <mcorrigan@harveyind.com.au>
Hi Matt,
BMS points list — confirm naming convention
Please advise by end of week.
Warren Lowe◷ Site coordination meeting — Penrith Golf Club HAC 31 Aug 2026 · 07:30
Attendees: Warren Lowe, Matt Corrigan, Luke Brennan. Plant delivery confirmed for crane lift; road closure permit lodged.
↗ RFI 013 — HAC-J2618 — Fire mode testing date with certifier HAC synced 19 Aug 2026 · 13:30
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Warren Lowe <warren@integratedprojects.com.au>
Hi Warren,
Fire mode testing date with certifier
Marked-up drawing attached.
Matt Corrigan◷ Site coordination meeting — Penrith Golf Club HAC 17 Aug 2026 · 07:30
Attendees: Warren Lowe, Matt Corrigan, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↗ Re: Quotation HAC-Q2643 — Penrith Golf Club — gaming & bistro upgrade HAC synced 18 Jul 2026 · 16:25
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Warren Lowe <warren@integratedprojects.com.au>
Thanks Warren — appreciated. Greg Pollard will be your project manager and will be in touch this week.
Rowan Kennedy↙ Re: Quotation HAC-Q2643 — Penrith Golf Club — gaming & bistro upgrade HAC synced 18 Jul 2026 · 10:00
From Warren Lowe <warren@integratedprojects.com.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan,
Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule.
Warren Lowe↗ Quotation HAC-Q2643 — Penrith Golf Club — gaming & bistro upgrade HAC sent 23 Jun 2026 · 14:07
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Warren Lowe <warren@integratedprojects.com.au>
Hi Warren,
Please find attached our quotation HAC-Q2643 for Penrith Golf Club — gaming & bistro upgrade — $386,500 + GST, valid 30 days.
Happy to walk through it.
Regards,
Rowan Kennedy