Seven Hills RSL — kitchen exhaust & make-up air · Seven Hills RSL Club
Demo 06 Oct 2026
← Contracts
✓
Quote accepted
HAC-Q2650
✓
Contract
Commissioning
✓
FBA fans
1/1 delivered
4
Practical completion
15 Oct 2026
5
Service handover
pending
ContractCommissioningOn track
Client
Seven Hills RSL Club · Melissa Grech
Site
Terminus Rd, Seven Hills
Project manager
Matt Corrigan
Program
28 Jul 2026 → PC 15 Oct 2026
Scope
Kitchen exhaust (FBA in-line), make-up air unit, hood interlocks.
From quote
HAC-Q2650
88% complete
MoneyForecast margin 21.5%
Contract value$214,000.00 Approved variations$3,100.00 Revised contract$217,100.00 Cost budget (from estimate)$179,200.00 Cost to date$148,876.00 Committed — FBA fans in build$0.00 Committed — open POs$0.00 Forecast final cost$170,380.00 Earned (88%)$191,048.00 Claimed to date$179,585.12 Retention held by client$8,979.26
Equipment $49,753 FBA fans (inter-company) $6,714 Ductwork (Parramatta shop) $23,171 Site labour $33,382 Controls subcontract $12,789 Electrical subcontract $8,867 Cranage & rigging $6,030 Pipework & materials $8,170
Equipment schedule1 FBA fan line(s) · 0 not yet ordered
TagTypeMake / modelLocationkWSupplyFBA works orderSerial
KEF-1 Kitchen exhaust fan In-line Centrifugal 630 backward inclined Roof 4 FBA WO-26126 · Dispatched FBA-26-0415
MUA-1 Make-up air unit MUA 2.4 kL/s Roof 3 Supplier — —
Costs to date$148,876
DateCategoryDescriptionAmount
11 Sep 2026 Site labour Site labour — weeks 7–9 $10,340
11 Sep 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 3 $7,998
11 Sep 2026 FBA fans (inter-company) WO-26126 In-line Centrifugal 630 backward inclined — KEF-1 Kitchen exhaust fan $6,714
07 Sep 2026 Pipework & materials Pipework & materials — claim 2 $3,880
07 Sep 2026 Cranage & rigging Cranage & rigging — claim 2 $3,288
07 Sep 2026 Electrical subcontract Electrical subcontract — claim 2 $4,031
07 Sep 2026 Controls subcontract Controls subcontract — claim 2 $6,205
07 Sep 2026 Equipment Supply — pumps $26,097
27 Aug 2026 Site labour Site labour — weeks 4–6 $11,883
27 Aug 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 2 $6,758
17 Aug 2026 Pipework & materials Pipework & materials — claim 1 $4,290
17 Aug 2026 Cranage & rigging Cranage & rigging — claim 1 $2,742
17 Aug 2026 Electrical subcontract Electrical subcontract — claim 1 $4,836
17 Aug 2026 Controls subcontract Controls subcontract — claim 1 $6,584
17 Aug 2026 Equipment Progress claim — CRAC units $23,656
12 Aug 2026 Site labour Site labour — weeks 1–3 $11,159
12 Aug 2026 Ductwork (Parramatta shop) Ductwork (Parramatta shop) — claim 1 $8,415
Emails & activity · 9
↗ RFI 026 — HAC-J2630 — Ceiling void clash with sprinkler main on grid C Matt Corrigan → Melissa Grech HAC synced 03 Sep 2026 · 15:45
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Melissa Grech <melissa@sevenhillsrsl.com.au>
Hi Melissa, Ceiling void clash with sprinkler main on grid C — can ductwork drop 150mm? Marked-up drawing attached. Matt Corrigan
◷ Site coordination meeting — Seven Hills RSL Meeting · Melissa Grech · Matt Corrigan HAC 01 Sep 2026 · 07:30
Attendees: Melissa Grech, Matt Corrigan, Luke Brennan. Program on track; ductwork L15 complete, L16 next week.
↙ RFI 023 — HAC-J2630 — Variation: additional FCU to comms room per tenant request Melissa Grech → Matt Corrigan HAC synced 20 Aug 2026 · 12:30
From Melissa Grech <melissa@sevenhillsrsl.com.au> · To Matt Corrigan <mcorrigan@harveyind.com.au>
Hi Matt, Variation: additional FCU to comms room per tenant request Please advise by end of week. Melissa Grech
◷ Site coordination meeting — Seven Hills RSL Meeting · Melissa Grech · Matt Corrigan HAC 18 Aug 2026 · 07:30
Attendees: Melissa Grech, Matt Corrigan, Luke Brennan. Plant delivery confirmed for crane lift; road closure permit lodged.
↗ RFI 020 — HAC-J2630 — Access to plantroom for crane lift Matt Corrigan → Melissa Grech HAC synced 06 Aug 2026 · 15:55
From Matt Corrigan <mcorrigan@harveyind.com.au> · To Melissa Grech <melissa@sevenhillsrsl.com.au>
Hi Melissa, Access to plantroom for crane lift — Saturday OK? Marked-up drawing attached. Matt Corrigan
◷ Site coordination meeting — Seven Hills RSL Meeting · Melissa Grech · Matt Corrigan HAC 04 Aug 2026 · 07:30
Attendees: Melissa Grech, Matt Corrigan, Luke Brennan. Builder requested look-ahead for ceiling close-up; agreed 2 weeks.
↗ Re: Quotation HAC-Q2650 — Seven Hills RSL — kitchen exhaust & make-up air Rowan Kennedy → Melissa Grech HAC synced 08 Jul 2026 · 16:31
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Melissa Grech <melissa@sevenhillsrsl.com.au>
Thanks Melissa — appreciated. Greg Pollard will be your project manager and will be in touch this week. Rowan Kennedy
↙ Re: Quotation HAC-Q2650 — Seven Hills RSL — kitchen exhaust & make-up air Melissa Grech → Rowan Kennedy HAC synced 08 Jul 2026 · 10:00
From Melissa Grech <melissa@sevenhillsrsl.com.au> · To Rowan Kennedy <rkennedy@harveyind.com.au>
Hi Rowan, Pleased to confirm we're proceeding — letter of award to follow from our contracts team. Please send your program and shop drawing schedule. Melissa Grech
↗ Quotation HAC-Q2650 — Seven Hills RSL — kitchen exhaust & make-up air Rowan Kennedy → Melissa Grech HAC sent 09 Jun 2026 · 14:51
From Rowan Kennedy <rkennedy@harveyind.com.au> · To Melissa Grech <melissa@sevenhillsrsl.com.au>
Hi Melissa, Please find attached our quotation HAC-Q2650 for Seven Hills RSL — kitchen exhaust & make-up air — $214,000 + GST, valid 30 days. Happy to walk through it. Regards, Rowan Kennedy